Quick to install embankment support

Technology from Tensar played a vital role along the Dishforth-Leeming section of the North Yorkshire A1 improvement work in northern England where new carriageways are being built adjacent to the existing in-use highway.
February 17, 2012 Read time: 2 mins
Technology from 340 Tensar played a vital role along the Dishforth-Leeming section of the North Yorkshire A1 improvement work in northern England where new carriageways are being built adjacent to the existing in-use highway.

By using a Tensartech TR2 Wall solution to create a temporary structure while raising a below grade section, the 2435 Carillion/2567 Morgan Sindall joint venture contractors are saving time and helping to minimise traffic disruption.

The existing 150m section of the A1 road either side of the Butcher House Bridge is up to 10m below the final required grade of the new motorway. An earth retaining structure with a near vertical face was required to support the new dual three-lane carriageway, which would allow the traffic to be switched to it while the old section was filled.

The conventional technique using extensive sheet piling along the embankment and for the bridge abutments to relieve lateral thrust would have been time consuming, and access for the equipment could have disrupted traffic flow.

Tensar developed a quick-to-install reinforced earth solution. With minimal disturbance to vehicles it temporarily supported the new south-bound embankment, bridge wing walls and abutments.

The contractor explained that as a temporary sacrificial structure, this was by far the best option and less expensive than other methods available.

The solution comprised compacted fill reinforced with layers of Tensar's uniaxial geogrid, securely connected to steel mesh facing units to form a 100m length of the 85˚ earth retaining structure up to 152 3M high; site won fill was used for this section.

For the bridge abutments and wing walls, a 26m length of vertical faced TR2 face, using imported granular fill and uniaxial geogrids, was built up to 9.5m. At either end of the embankment, a 45˚ slope was constructed using Tensartech.

For more information on companies in this article

Related Content

  • The A14 Cambridge to Huntingdon improvement scheme takes shape
    May 31, 2017
    Highways England’s project manager gives sneak peek into progress on the UK’s biggest road upgrade now under construction. Road construction workers often find interesting buried items when building roads and the UK’s A14 Cambridge to Huntingdon improvement scheme is proving the point. It’s been less than half a year since construction started on the €1.76 billion A14 scheme, Highways England’s largest ongoing project. Highways England is the wholly government-owned company responsible for modernising, main
  • India’s capital highway project will improve transport connections
    October 10, 2017
    Huge numbers of construction machines as well as plant and equipment are working overtime, backed by mammoth manpower, to meet the targeted completion deadline of March 2018 for India’s Eastern Peripheral Expressway (EPE). The 135km arterial route is being built with six lanes and surrounds India’s National Capital, Delhi, its National Capital Region (NCR) and the industrially developed North Indian states of Haryana and Uttar Pradesh.
  • Scottish mountain highway toast to SuDS
    June 24, 2013
    Highway degradation and surface water pollution in an environmentally sensitive area of the Scottish Cairngorms Mountains, famous for its whisky production, are said to have been tackled with an innovative SuDS Solution from Hydro International. Poor drainage, flooding and freezing weather had led to a landslip and extreme surface degradation along a section of the narrow A95 that descends on a 10% gradient with tight bends to the beautiful village of Craigellachie on the River Spey, near Elgin. Situated im
  • Mexico’s new Jala-Puerto Vallarta Highway
    August 29, 2017
    Mexico’s highway infrastructure plays a key role in the country’s economy, carrying around 55% of its freight and 98% of its passenger traffic. To meet this demand, the network has 377,660km of roads in all. This is split between the 49,652km federal highway network, the 83,982km of state roads, 169.429km of rural roads and 74,596km of access roads. mHowever, although the federal road network manages to connect a large part of the country's strategic points, some stretches already present problems with satu