Quick to install embankment support

Technology from Tensar played a vital role along the Dishforth-Leeming section of the North Yorkshire A1 improvement work in northern England where new carriageways are being built adjacent to the existing in-use highway.
February 17, 2012 Read time: 2 mins
Technology from 340 Tensar played a vital role along the Dishforth-Leeming section of the North Yorkshire A1 improvement work in northern England where new carriageways are being built adjacent to the existing in-use highway.

By using a Tensartech TR2 Wall solution to create a temporary structure while raising a below grade section, the 2435 Carillion/2567 Morgan Sindall joint venture contractors are saving time and helping to minimise traffic disruption.

The existing 150m section of the A1 road either side of the Butcher House Bridge is up to 10m below the final required grade of the new motorway. An earth retaining structure with a near vertical face was required to support the new dual three-lane carriageway, which would allow the traffic to be switched to it while the old section was filled.

The conventional technique using extensive sheet piling along the embankment and for the bridge abutments to relieve lateral thrust would have been time consuming, and access for the equipment could have disrupted traffic flow.

Tensar developed a quick-to-install reinforced earth solution. With minimal disturbance to vehicles it temporarily supported the new south-bound embankment, bridge wing walls and abutments.

The contractor explained that as a temporary sacrificial structure, this was by far the best option and less expensive than other methods available.

The solution comprised compacted fill reinforced with layers of Tensar's uniaxial geogrid, securely connected to steel mesh facing units to form a 100m length of the 85˚ earth retaining structure up to 152 3M high; site won fill was used for this section.

For the bridge abutments and wing walls, a 26m length of vertical faced TR2 face, using imported granular fill and uniaxial geogrids, was built up to 9.5m. At either end of the embankment, a 45˚ slope was constructed using Tensartech.

For more information on companies in this article

Related Content

  • Building Egypt's world class Desert Highway
    February 9, 2012
    A huge highway upgrade project will transform the Cairo-Alexandria road link into a world-class connection as Mike Woof reports
  • Upgrade for Scottish road
    February 17, 2012
    Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between
  • Efficient earthmoving builds new road links
    February 7, 2012
    Efficient earthmoving is allowing productive road construction in the Egyptian desert, Mike Woof reports. Despite ferocious desert temperatures, efficient earthmoving operations will help build new road links in Southern Egypt. Close to the Egyptian city of Assuit, the contractor Orascom is working on three key desert highway projects that will provide vital transport connections for the country's growing economy.
  • Key expressway route through Hunter Valley
    November 11, 2013
    Australia’s Hunter Valley will benefit from a new high speed expressway, which is currently under construction - Simon Gould reports Located two hours north of Sydney, the Hunter Valley region in New South Wales is one of Australia’s largest producers of coal and wine. With international demand, particularly from Asia, for both continuing to increase, a significant upgrade of infrastructure was required between the region and the port of Newcastle, the world’s largest coal export port. However the strict en