Pilosio has supplied a set of 18 MP high-capacity towers for the construction of a viaduct on the Bellinzona-Lugano section of the new trans-Alpine railway, due for completion by the end of 2014. The viaduct is divided into five sectors of varying distances, from 110m for the first to 100 for the second. Both were due to be completed this month. The third and fourth sectors will be 90m long, while the fifth will span 45m – forming a flyover across Strada Cantonale, which links Locarno and Bellinzona.
July 1, 2013 Read time: 2 mins
A set of 18MP high-capacity towers from Pilosio are said to be saving vital time in the construction of a viaduct on the new trans-Alpine railway
7163 Pilosio has supplied a set of 18 MP high-capacity towers for the construction of a viaduct on the Bellinzona-Lugano section of the new trans-Alpine railway, due for completion by the end of 2014.

The viaduct is divided into five sectors of varying distances, from 110m for the first to 100 for the second. Both were due to be completed this month. The third and fourth sectors will be 90m long, while the fifth will span 45m – forming a flyover across Strada Cantonale, which links Locarno and Bellinzona.

Project client the MPC Consortium, made up of firms CSC SA, Mutoni SA and Pizzarotti SA, decided to construct 18 concrete pillars for each of the viaduct’s five sectors. The pillars were only to be used to support the construction of the upper structure and would then have to be demolished once the building work had been finished. However, Pilosio said the decision to use its MP high-capacity towers – coupled in pairs by horizontal stiffeners allowing them to be moved en masse from sector to sector - meant that significant time could be saved instead of waiting for the concrete of the support pillars to be fully set. The Italian firm said this allowed better continuity between the striking of the formwork of one sector and the assembly of the support structure for the next sector.

The adjustment of the heights of the towers to the height of the viaduct is said by Pilosio to be achieved by adjusting the forks and the reinforced base plates. Pilosio said the use of its towers for the viaduct works allowed the best number of workers to be employed in the assembly and dismantling phases, enabling a major financial saving through reduced material use.

For more information on companies in this article

Related Content

  • World’s largest bridge deck for KAIA expansion
    December 16, 2013
    A bespoke formwork solution from RMD Kwikform is playing a key role in creating the largest ever airport cast bridge deck as part of the multi-billion dollar expansion of King Abdulaziz International Airport near Jeddah, Saudi Arabia. The firm is also a leading player in the creation of arterial tunnels under the airport’s elevated roads, another key part of the project’s first phase works due for completion in 2014. Guy Woodford reports
  • Italy's strategic tunnel link
    August 21, 2012
    The world's largest tunnelling machine is completing Italy's important road connection between Bologna and Florence - Adrian Greeman reports For just under a decade a huge programme of highway construction has been underway in the mountainous region between Bologna and Florence, realigning a section of the A1 highway nearly 70km long. The new section, through major tunnels and across high viaducts, will greatly increase capacity on Italy's most important highway.
  • Curved girders for the Gaasperdammerweg A9 section in Amsterdam
    May 22, 2018
    Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of Ballast Nedam, Fluor, Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section
  • Mullum Mullum Valley untouched by progress
    July 20, 2012
    Preserving the unspoiled Mullum Mullum Valley was the major consideration when deciding to build a traffic tunnel The answer to one of the major issues facing construction of the A$2.5 billion EastLink route in Australia was simple: construct a tunnel. While it was expensive, those involved realised they had little option but to go underground to protect the environmentally sensitive Mullum Mullum Valley, an untouched area of wood and bushland in Melbourne. EastLink, the 39km toll road project on the easter