Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • Developments in concrete pavers boosts quality
    July 13, 2012
    The latest technology continues to improve the quality of concrete paving while contractors are also benefiting from more adaptable equipment - Mike Woof reports For many concrete paving applications, versatility is required rather than a high production rate. Leading paver manufacturers such as GOMACO, Power Curbers, Terex and Wirtgen all offer high mobility machines that can be adjusted to cope with an array of tasks. For a contractor, the advantage of these smaller pavers is that they can be configured q
  • Optimised machines improve aggregate production
    February 27, 2012
    Improving aggregate production and quality levels is not just about investing in the latest equipment but making sure existing machines are optimised - Claire Symes reports. Although the cost of fuel has dropped since last summer's high, reducing the cost/tonne of production is still high on the agenda for most quarry operators, along with improving quality.
  • Controlling influence
    January 3, 2013
    New lane control solutions from major roadmarking companies have been installed on highways across the world over recent months. Guy Woodford reports on some of them. Clearview Traffic Group (CTG) recently clocked up the installation of over 70,000 Astucia active flush and surface mounted road studs in the UK. CTG has been involved in numerous road stud installation projects on motorways and other road types in the UK and many other countries worldwide. Its UK installations include over 4,500 Astucia road s
  • The UK’s A14 route is seeing a major upgrade
    June 14, 2018
    Work is progressing well on the project to upgrade the busy A14 route in the UK. A major milestone has been achieved with and important phase of the bridge installation having taken place. A 39m viaduct beam has been placed successfully for the bridge, which spans the River Ouse in Cambridgeshire. A key role in this work has been taken by the firm Cleveland Bridge UK. As part of Highways England’s £1.5 billion A14 Cambridge to Huntingdon improvement scheme, Cleveland Bridge was contracted by the A14 Integr