Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • Workzone safety protects workforce and drivers
    May 3, 2012
    Highway construction work zones are dangerous places, and anything that can improve safety is welcomed as Patrick Smith reports. The safe and efficient flow of traffic through work zones is a major concern to transportation officials, industry, the public, businesses, and commercial motor carriers. This is the view of the US Federal Highway Administration (FHWA), which has developed the Highway Work Zone Safety Program to reduce the fatalities and injurious crashes in work zones, and to enhance traffic oper
  • Asphalt plants looking at greener production systems
    April 11, 2012
    A wide variety of new equipment and technology to assist production at asphalt plants is about to be launched onto the market, while asphalt producers are continuing to look at greener working practices. Guy Woodford reports Lintec, in partnership with Loesche, recently created what they say is the world's first containerised Coal Mill Plant for independent coal dust supply at the jobsite which offers mobility and high economic efficiency through the substitution of gas or oil with coal. The mobile co
  • Florida highway rebuild project
    May 2, 2018
    Rebuilding a congested stretch of highway in Florida will cut congestion and boost safety for commuters - Mike Woof writes. Florida’s 214km-long I-4 highway provides a key transport route between Tampa and Daytona Beach, but has an unenviable reputation for both congestion and safety, with frequent delays due to heavy traffic as well as crashes. The stretch running through the city of Orlando is particularly prone to jams at peak periods, with huge traffic volumes resulting in vehicles having to slow to a c
  • Poetry in motion
    August 9, 2018
    A heavy-lift operation by Roll-iT using Enerpac equipment delivered a bridge deck - with a poem engraved on the underside - to Antwerp’s old harbour Only when the deck of the new Londenbrug Bridge is raised do travellers see the poem by Antwerp poet Stijn Vranken. It is written large on the underside of the 300tonne prefabricated steel deck. People waiting for a ship to pass the raised bridge now contemplate the poem’s message about ships transporting goods and people to and from the four corners of the