Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • Kontent Structures has it covered
    October 15, 2021
    Renovation on a bridge over the Rhine River in Karlsruhe, Germany, has been completed using a weather-resistant tent covering the entire length of the structure
  • Auckland Harbour bridge celebrates 50 years
    April 5, 2012
    The bridge over Auckland Harbour celebrates its half century this year, and it has been given a major upgrade to ensure that safety is maintained in New Zealand's largest city. Mary Searle reports. Auckland is New Zealand's largest city, home to nearly a third of the entire country's population. It's a sprawling metropolis, and its 1.3 million people are spread over 637km² of city, suburbs and islands. The Auckland Harbour Bridge, which celebrates its 50th birthday in May, is a vital link in the city's road
  • Auckland Harbour bridge celebrates 50 years
    February 22, 2012
    The bridge over Auckland Harbour celebrates its half century this year, and it has been given a major upgrade to ensure that safety is maintained in New Zealand's largest city. Mary Searle reports. Auckland is New Zealand's largest city, home to nearly a third of the entire country's population. It's a sprawling metropolis, and its 1.3 million people are spread over 637km² of city, suburbs and islands. The Auckland Harbour Bridge, which celebrates its 50th birthday in May, is a vital link in the city's road
  • New German autobahn bridge under constriuction
    May 1, 2015
    Crane manufacturer Manitowoc has supplied six Potain cranes to German contractor Max Bögl. These machines are being used for constructing a new bridge carrying the A3 autobahn, close to Limburg. Working at over 70m high, the cranes tower over the Lahn Valley. The cranes for this project were supplied by Max Bögl’s subsidiary, Max Bögl Transport & Geräte. The three topless Potain MDT 222 cranes were selected for the work as they feature tip heights of up to 76.2m and can operate with a working radius of