Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • Progression in concrete plant and mixing solutions
    July 14, 2014
    Big orders for and progress in plant and concrete mixing technology has been continuing at a rapid pace over recent months, as Guy Woodford reports Shantui recently completed an eye-catching US$3.2 million deal with a customer in the United Arab Emirates for 50 concrete mixer trucks. The deal is said to be an important breakthrough for the Chinese company’s concrete machinery in the Middle East market, raising brand awareness and laying a solid foundation for building market share. Over the past y
  • Vietnam tunnel construction project
    November 21, 2016
    A new tunnel link in Vietnam will help boost road safety for drivers. This new twin tube tunnel connection will replace, the Ca Mountain Pass, a steep and dangerous mountain route in Vietnam
  • Rural Czech roads get paving upgrade
    November 2, 2012
    A series of rural road rebuilds have improved transport connections in the Czech Republic, helping to boost connectivity and the local economy The roads around Brandýs nad Labem, some 25km to the southwest of Czech capital Prague are crucial arteries to the rural and agricultural areas of the country. An assessment by regional authorities indicated that these roads are in need of repair. That led to cold planing and paving work on a series of rural roads near Brandýs nad Labem. The regional authorities had
  • India plans major infrastucture investment
    February 10, 2012
    India says it turned its Commonwealth Games into a world-class success, and now it aims to do the same with its infrastructure. Patrick Smith reports. On October, 2010 India put itself on the world stage, and disaster appeared to loom as a catalogue of problems dogged its biggest ever sporting event. Costing nearly US$2 billion to stage, the most expensive Commonwealth Games ever were, according to some, in doubt.