Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • Delayed Houston Ship Canal Bridge nearing first phase
    February 23, 2024
    The delayed Houston Ship Canal Bridge is nearing its first phase completion.
  • A 'roller coaster' ride
    July 16, 2012
    The Gold Coast region in the Australian state of Queensland is internationally renowned as a tourist area attracting thousands of visitors from Brisbane, where the state's biggest ever road and bridge upgrade project is currently underway. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels: the north is getting a completely new 7km section of motorway on a different alignment to bypass extra traffic, and tolls are being automated to speed flow
  • EastLink tollway a winner at the 9th ITS Australia National Awards
    June 4, 2019
    The Freeway Tunnel Ventilation On-Demand System for Melbourne’s EastLink project picked up the top Industry Award category at the recent 9th ITS Australia National Awards Traditional tunnel ventilation systems are inefficient. Fans operate at fixed speed in manual mode or with individual fans programmed to switch on and off at preset times to ensure zero portal emissions with all emissions dispersed via ventilation stacks. EastLink’s new ventilation on demand – VoD - system matches variable speed fan
  • Ammann machines helping build infrastructure in Bangladesh
    May 16, 2018
    Soil and asphalt compaction machines from Ammann are working on two key infrastructure projects in Bangladesh. The units are being used by local contractor Spectra Engineers, which is based in Dhaka. The firm has a strong reputation in Bangladesh for quality and is relying on Ammann soil and asphalt compactors for a number of projects. Spectra is one of the leading construction companies in Bangladesh, with considerable expertise and experience building roads and bridges for example. Spectra is working on