Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • Volvo CE’s electric quarry operation commences trials
    August 29, 2018
    Volvo CE is commencing operations of its low emission quarrying operation in Sweden. The facility has a strong focus on electric machines, with diesel-electric hybrid equipment also being used. According to the firm, this is a world first for a quarry facility that can be run almost 'emission-free'. Volvo CE and its customer Skanska have now commenced testing the viability of the Electric Site concept at Skanska’s Vikan Kross quarry, located near Gothenburg in Sweden. The production system at the site
  • Effective crushing and screening key to quality
    February 22, 2012
    Efficient crushing and screening processes help produce quality products, Mike Woof reports. Having an efficient crushing and screening operation is crucial to the cost-effectiveness of a quarry as well as providing the best quality product. The crushing circuit is a key component in any quarry with the right selection of equipment as well as effective maintenance important factors in optimising performance.
  • MatTracker ensures densities at lane joints
    April 18, 2016
    TF-Technologies which specialises in technology related to asphalt paving has invented a new means of ensuring asphalt density along the longitudinal joints between lanes. The MatTracker, developed just in time for bauma 2016, ensures that the lap width is correct and controls the position of the paver.
  • Major gains in concrete plant technology
    June 28, 2013
    There is a great deal of innovation across the concrete plant, pump and truck mixer sector. Guy Woodford looks at what some of the sector’s biggest names are offering. CIFA managing director Davide Cipolla believes the Zoomlion-owned Italian firm has “not reached the limit” of what it can offer customers, thanks to a significant investment in research and development. Speaking about a US$2.57 million-a-year (€2million) R&D investment in CIFA and some Zoomlion products over the last five years Cipolla, who i