Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • New NY Bridge - Tappan Zee - main span towers poured
    December 16, 2016
    One of the largest US infrastructure projects is nearer completion after recent topping out of the eight main span towers of the New NY Bridge. The final concrete pour was in mid-December and all piles - more than 1,000 - have been installed in Hudson River. To date, 3,000 roadway panels for the approaches - making 5.5km in length - have been installed, according to the New York State Thruway Authority, owner of the New NY Bridge project. The New NY Bridge, also called the Tappan Zee Bridge, is on tra
  • The Lessons of the Genoa bridge collapse
    April 23, 2019
    The partial collapse of the Polcevera viaduct, better known as the Morandi Bridge, has prompted debate regarding the technical and administrative aspects of maintaining road infrastructures. We discussed it with the engineer Gabriele Camomilla, former Director of Research and Maintenance of the Società Autostrade, who coordinated the only major structural intervention performed on the bridge, carried out in the early 1990s
  • Using breakers to demolish redundant overpass
    December 11, 2015
    A demolition job in California was carried out successfully using a hydraulic breaker fitted to an excavator. An overpass on Highway 91 in Southern California had to be removed, with the contractor opting to use a hydraulic breaker for the job. The work was carried out within the 22-hour possession period set by the local authorities, allowing the route to reopen to traffic on time and minimising transport delays. The work was carried out safely and precisely, due to the use of suitable equipment. The re
  • The concrete option
    July 31, 2012
    Concrete highway construction techniques and technology continues to evolve. Mike Woof reports The recent increases in oil costs are having a knock-on effect for the road construction sector, as asphalt prices have increased noticeably and faster than those for concrete. This has spurred renewed discussion over which construction technique now offers the best long term solution for road building. The debate between those in favour of concrete and those preferring asphalt for highway construction has been on