PERI fills gap in Greek market

A team of Greek and German PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece. The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arc
February 19, 2013 Read time: 3 mins
The VARIOKIT heavy-duty shoring towers being used on the T4 bridge on the A7 motorway in Greece are transferring a combined 2,400tonnes load
A team of Greek and German 298 PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece.

The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arch and realised using the steel composite construction method. For the northern bridge section, a pre-stressed concrete superstructure variant was selected which features a twin-cell hollow box cross-section.

The supporting element of the motorway bridge is a huge, almost 30m high inclined twin-pillar pier with an asymmetric V-shape. This serves as an intermediate support for the in-situ concreted carriageway. It also serves as a support and starter section for the steel arch. Engineers from PERI and Greek colleagues devised a cost-effective plan for constructing the pier structure, the reinforced concrete superstructure and the temporary support for the bridge during the entire building project

The chosen two modular construction systems combine with each other to transfer the high loads safely into the ground. With help of the PERI UP Rosett Flex modular scaffold system, forming a spatial load-bearing structure for the piers and superstructure formwork, a gradual increasing up to the total support height of over 20m was achieved to the rear and upwards respectively. By means of 25, 50 and 75cm long ledgers, the 150cm basic grid is said by PERI to have been adapted to suit the geometric and static requirements extremely flexibly. This allowed the polygonal 32° to 36° shallow pitched inclined piers on both sides of the bridge to be constructed in eight segments, each 4.5m long.

In addition to the PERI UP scaffold construction being used, the VARIOKIT engineering construction kit, in particular, is said to offer standardised system solutions for tunnel, bridge and civil engineering projects. Thus, trusses consisting of rentable standard elements support the obliquely-positioned VARIO GT 24 girder formwork and transfer the formwork and concreting loads of the inclined piers safely into the scaffolding.

The VARIOKIT modular construction system also forms the basis for the heavy-duty shoring. In the connecting area between the cast-in-place bridge and steel arch, two 17m high, 42-leg VARIOKIT heavy-duty shoring towers are used to accommodate the high loads – throughout the entire construction period until the inherent load-bearing capacity is reached. Each of the two towers has to carry loads of 1,200tonnes and, due to the long utilisation time, has to cater for high earthquake-induced as well as horizontal loads. Here, PERI engineers combined four standard towers, each with a 2m by 2m axis dimension, by means of several bundled 37.5cm additional frames (number depended on the load concentration) to form two power packages. Only rentable system components and construction-compliant, type-tested connection means were said by PERI to be used for this.

For more information on companies in this article

Related Content

  • Svevia in Fjälkinge and Gualöv motorway deal
    April 7, 2023
    Under the contract in southern Sweden - worth around €45 million - the state-owned civil engineering company will also construct six bridges of which two will be fauna passages.
  • Pöyry picks up tunnel project on Switzerland’s A2 motorway
    August 18, 2016
    The Swiss Federal Roads Office (FEDRO) has awarded Poyry detailed engineering planning work for the upgrading of operational and safety equipment in two major tunnels on the A2 motorway. The A2 forms the main north-south motorway in Switzerland, connecting Basel with Chiasso. The Schänzli and Hagnau tunnels have been in operation for four decades and are being completely refurbished. Pöyry has already been handling the structural measures and ventilation systems in the tunnels, said Marcel Winter,
  • High profile for Blastcrete’s low-profile Mine Mate
    April 4, 2018
    If ready-mix concrete is not an option for underground sealing, stabilisation and grouting, then Blastcrete Equipment’s Mine Mate will step up. The low-profile Mine Mate mixes and pumps concrete material for shotcrete applications. It features Blastcrete’s X-10 ultra high-pressure swing tube pump for the wet-mix shotcrete process. In contrast to the dry shotcrete – gunite - the wet shotcrete process minimises dust and improves visibility making it much safer, particularly for underground use. Featuring a co
  • Plans moving forward for key Turkish highway
    October 11, 2013
    Plans are moving forward in Turkey for the construction of a new highway project. Mott MacDonald has been named lenders’ technical advisor by the IC Ictas-Astaldi (ICA) consortium for a 60km section of the Northern Marmara highway. This deal is significant and the stretch forms the first of a number of phases of the highway. The project is being delivered under a 10 year, US$2.5 billion public-private partnership (PPP).