Norway’s Beitstad Bridge opens

Norway has officially opened the Beitstad Bridge over the Beitstad Sund, between the towns of Steinkjer and Verran in Nord-Trøndelag County.
June 22, 2020 Read time: 2 mins
Sarens barged the bridge segments from Malm to the construction site (photo courtesy Sarens)

The 580m-long steel-concrete composite bridge, constructed by China’s Sichuan Road and Bridge Group (SRBG), is part of Norway’s County Roads 17 and 720. The company won the contract through an open tender and finished the project in 26 months.

Last September, heavy lifting specialist Sarens finished installing six pre-assembled bridge segments, varying between 40-150m long and up to 15m wide. The segments weighed between 130-780tonnes. Sarens barged the bridge segments from Malm to the construction site, a distance of about 5km. The crew also used a 24-axle SPMT (self-propelled modular transporter from Mammoet), a Kobelco hydraulic CKE-2500 crawler crane and a Terex-Demag CC8800-1 crawler crane. The CC8800-1 had a capacity of 1,600tonnes and was fitted onto the barge to perform all heavy lifts.

Sarens said that this was the first time a CC8800-1 crane had been used to install bridge elements from a Sarens barge. It was loaded onto a barge in Gent, Belgium, and towed to Malm in Norway by tugboat - an eight-day voyage. The crane was then configured in SSL MB 84m configuration for the first four lifts and the main boom was lengthened to 120m for the last two elements.

The crew lifted the first segment on day one and the sixth and final segment on day 14 – a two-week time frame set by the client, according to Joost Elsen, Sarens operations head who oversaw the work. “Challenges for the lifting were for once not the movement of the crane, but the exact positioning of the barge as we intended to minimise crane movements to only boom up and down to the installation radius.”

Main contractor SRBG says that its expertise lies in construction of deepwater long-span bridges, highway pavements and extra-long tunnels. Much of the company’s management team for the Beitstad Bridge came from the recently completed Halogaland Suspension Bridge, 200km north of the Arctic Circle. The Halogaland Bridge crosses the Rombaksfjorden in Narvik Municipality in Nordland County. Construction began in February 2013 and finished in December 2018 when it opened to traffic.

For more information on companies in this article

Related Content

  • Giving credence for Clearwater revival
    October 29, 2018
    The Minnesota Highway 24 Bridge spanning the Mississippi River at Clearwater is not a major structure. However, it does play a key role as the 376.4m-long bridge links US Highway 10 and Interstate 94. These routes run parallel on opposite sides of the Mississippi River and connect St Cloud to Minneapolis. There was a need to replace the old bridge, built in the 1950s, as it has been designated functionally obsolete, while it featured a restricted maximum load of 36.3tonnes. The price tag to demolish and
  • Sykes Pumps ballasting expertise adds weight to Forth float-outs
    June 17, 2016
    UK hire specialist, Sykes Pumps, is playing a vital role in delivering Scotland’s biggest transport infrastructure project in a generation - The Forth Replacement Crossing (FRC). Once completed later this year, the new road bridge will be the longest three-tower cable-stayed bridge in the world. Forth Crossing Bridge Constructors (FCBC) consortium is using 42,000 tonnes of steel. Getting all that steel out into the Firth of Forth is a delicate operation. The project involves transferring 7,000tonne se
  • Mammoet orders 17 cranes from Kobelco
    April 13, 2016
    Mammoet, one of the world market leaders in the field of engineered heavy lifting and transport, has ordered 17 Kobelco cranes for its worldwide operations. Included in the deal are 15 cranes of the second generation CKE-/BME-G-series, equipped with the new engine in compliance with NRMM Europe Stage IV and US EPA Tier 4 Final regulations. These include three CKE1100-2 with 110tonne maximum lifting capacity; seven CKE1350G-2 (150tonne lifting capacity) and five CKE2500G-2 (250tonne lifting capacity).
  • Manitowoc crane helps construct new Illinois bridge
    December 15, 2017
    A barge-mounted crane from Manitowoc is playing a key role in a major Illinois bridge replacement project. The machine is being used by Kraemer North America, which is replacing an 84-year-old truss bridge near Savanna, Illinois. The firm is employing a barge-mounted MLC300 equipped with the sophisticated variable position counterweight (VPC) technology, which is said to allow the MLC300 to adjust its counterweight during each lift and keep the barge stable while lifting. When Manitowoc introduced its VPC