New bridge surfacing

A new wearing course applied by Bolidt on the entire eastern section of the Erasmus Bridge in Rotterdam is helping improve the surface for road users. The bridge forms an important link in the centre of the city of Rotterdam and using its equipment Bolidt was able to apply 3,000m2 of new wearing course on Erasmus Bridge in 4 hours. The Rotterdam authorities commissioned Bolidt again after the previous surface the firm applied, its Bridgedeck Up product, lasted over a decade. This time the work was carried o
February 6, 2012 Read time: 2 mins
Using Bolidt's technology to resurface a Rotterdam bridge cut installation time
A new wearing course applied by 2291 Bolidt on the entire eastern section of the Erasmus Bridge in Rotterdam is helping improve the surface for road users. The bridge forms an important link in the centre of the city of Rotterdam and using its equipment Bolidt was able to apply 3,000m2 of new wearing course on Erasmus Bridge in 4 hours. The Rotterdam authorities commissioned Bolidt again after the previous surface the firm applied, its Bridgedeck Up product, lasted over a decade. This time the work was carried out using a machine developed by Bolidt, speeding installation.

Although the previous wearing course was still intact, the decision to replace it was made as part of a maintenance operation. Over one weekend, the entire eastern section of the bridge was resurfaced with a new wearing course and lining. The work was carried out in less than 36 hours due to the equipment used and this high productivity was of key importance as Rotterdam has a heavy traffic load and a prolonged closure would have resulted in serious congestion.

The Bolimix machine was developed by Bolidt originally for the application of wearing courses on concrete bases. The Erasmus Bridge has a steel base, which requires a different type of wearing course and Bolidt had to adapt the machine especially for the work. Exchangeable tanks, allowing a short conversion time, were made to achieve this. Where in the past it was necessary to have several days of dry weather, this has now been reduced to approximately 1.5 days. After the wearing course has been applied, rain no longer forms a hindrance.

For more information on companies in this article

Related Content

  • How Croatia tackles its weight problems
    July 19, 2012
    Karin Junker, Regional Sales Manager Eastern Europe and Russia, HAENNI Wheel Load Scales, Switzerland, looks at weight enforcement in Croatia Croatia's modern period in history began in 1990 with the country's change of political and economic system, and the achieving of independence from Yugoslavia on 25 June, 1991. The country remained war torn during the 1990s but regained stability and economic growth after the turn of the millennium. During a recent trip to Croatia to visit HAENNI's distributor in t
  • Controlled demolition development
    January 25, 2017
    The development of reliable hydraulic attachments has brought a revolution in demolition technology. The hydraulic breaker, pioneered by the Krupp and Montabert brands, has firmly taken hold with a huge range of manufacturers now offering machines. Hydraulic attachment specialists such as Atlas Copco, Indeco and Sandvik (with its Rammer brand) now offer a range of tools that can deliver high efficiency and safety in demolition work. Meanwhile, developments with smaller tools offer productive methods for rep
  • Surfaces made safe
    February 10, 2012
    Spanning Manahawkin Bay, and carrying traffic along Route 72 between Long Beach Island and Manahawkin, New Jersey, USA, the Dorland J. Henderson Memorial Bridge, known as the Manahawkin Bay Bridge, was in need of repair. New Jersey Department of Transportation (NJDOT) specified Transpo T-17 MMA polymer concrete patch and T-18 MMA polymer concrete slurry overlay as approved materials for the 12,000m² bridge rehabilitation project on the steel girder bridge. All the bridge deck spalls were prepared and patche
  • Surfaces made safe
    April 4, 2012
    Spanning Manahawkin Bay, and carrying traffic along Route 72 between Long Beach Island and Manahawkin, New Jersey, USA, the Dorland J. Henderson Memorial Bridge, known as the Manahawkin Bay Bridge, was in need of repair. New Jersey Department of Transportation (NJDOT) specified Transpo T-17 MMA polymer concrete patch and T-18 MMA polymer concrete slurry overlay as approved materials for the 12,000m² bridge rehabilitation project on the steel girder bridge. All the bridge deck spalls were prepared and patche