New bridge for old Russian city

Murom, one of Russia's best preserved old cities, is situated in the European part of the country, around 300km to the east of Moscow. The most important industry and economic activities are mechanical engineering along with timber and textiles. The location on the River Oka, a tributary of the Volga and thus an important waterway, as well as the good connections to important main roads and rail routes, are positive economic factors. It is near Murom that German formwork and scaffolding specialist PERI is p
July 30, 2012 Read time: 3 mins
Impressive: The cable-stay bridge over the River Oka features two 231m spans and is carried by three pylons with heights of around 90m. Photo: PERI
Murom, one of Russia's best preserved old cities, is situated in the European part of the country, around 300km to the east of Moscow.

The most important industry and economic activities are mechanical engineering along with timber and textiles.

The location on the River Oka, a tributary of the Volga and thus an important waterway, as well as the good connections to important main roads and rail routes, are positive economic factors.

It is near Murom that German formwork and scaffolding specialist 298 PERI is providing a complete range of services for the construction of the three 90m high bridge piers.

Positioned at distances of 231m from each other respectively, these have been designed to carry the loads of the cable-stay construction which will span the River Oka at a height of 30m. The bridge is scheduled to be opened in 2009.

Underneath the carriageway, the cross-sectional form and dimensions of the pylon legs are continuously changing and the pentagonal basis transforms into a rectangle at height of the carriageway slab. In addition, the resulting outside pylon edges exhibits a curvature with a 300mm radius. From the top edge of the carriageway upwards, the shape and dimensions in a lateral direction remain constant for the most part; in a longitudinal direction, however, the external dimensions of the pylon tapers from 6-3m.

For the 21 concreting sections in each case, with 3.67m standard cycle heights, PERI engineers designed customised climbing formwork solutions and, in so doing, relied on the flexibility of the PERI VARIO girder wall formwork. In connection with workflow-oriented execution planning, all required adjustments can be carried out on the variable cross-sections from cycle to cycle with a minimum of time and effort. Together with the PERI CB climbing scaffold system for the vertical and slightly inclined areas as well as SKS/SSC brackets of the PERI SKS single-sided, retractable climbing formwork for the forward and reversed-angled sections, fully adaptable climbing formwork units are formed. On each of the pylon legs, the four scaffold platforms along with the re-adjusted formwork for each concreting section is climbed by means of a single crane pick.

"As a cost-effective solution for non-standard and unusual architect demands as well as any kind of special designs, PERI also delivers pre-assembled 3D formwork units directly to the construction site," says the company.

"For the Murom bridge, these serve to accurately form the contours of the pier geometry at the bottom, and are attached to the inside of the VARIO formwork at the front." The customised individual units were produced in Weissenhorn at the company's 866 CNC timber processing plant but then shipped to Russia in the form of compact construction kits.

"Due to the precision-made formed components complete with insertion slits, the clear markings and an exact construction plan, joining was able to be carried out on site with only a minimum of effort." The contractor is 2450 Mostotrest of Moscow, and field service is by PERI Moscow and Weissenhorn.

For more information on companies in this article

Related Content

  • Russian bridge project well underway
    November 3, 2017
    Construction work on Russia’s Frunzensky Bridge is now well under way. The bridge spans the Samara River, a tributary of the Volga River and was originally planned for completion by 2018. The construction company Stroytransgaz has a US$213.5 million contract to finish the project and the bridge is now expected to be ready for traffic by 2020. The bridge project did face challenges from insufficient funding and cost increases but the necessary financing package is now in place. When complete the bridge is in
  • Bridge deck launched for the New Wear Crossing, Sunderland (Video)
    March 30, 2017

    The 300m bridge deck of Sunderland’s New Wear Crossing has been successfully launched across the river.

    The 4,750tonne concrete and steel deck was resting on the south side of the River Wear from where it was inched across to touch the north side in a 20-hour operation. It had to slide through the twin arched towers of the bridge’s double pylon on its way to its final position to connect the city regions of Pallion to the south and Castletown to the north.

  • Alberta’s peaceful partnership
    May 4, 2020
    A bridge project in northern Canada threw up some unexpected challenges, reports David Arminas, from the banks of the Peace River in Alberta
  • Key Russian highway projects in planning
    November 30, 2015
    Construction of the Russian stretch of the highway connecting Europe with China should be complete by 2018. This section of the project is costing close to US$22.6 billion. The international transit corridor from Europe to Western China is of key economic significance. The first sections of the Russian portion of the route form part of the new high-speed federal highway M-11 from Moscow to St Petersburg. About 40% of the highway will run through the Volga federal district. The 8,400km long international tra