New bridge for old Russian city

Murom, one of Russia's best preserved old cities, is situated in the European part of the country, around 300km to the east of Moscow. The most important industry and economic activities are mechanical engineering along with timber and textiles. The location on the River Oka, a tributary of the Volga and thus an important waterway, as well as the good connections to important main roads and rail routes, are positive economic factors. It is near Murom that German formwork and scaffolding specialist PERI is p
July 30, 2012 Read time: 3 mins
Impressive: The cable-stay bridge over the River Oka features two 231m spans and is carried by three pylons with heights of around 90m. Photo: PERI
Murom, one of Russia's best preserved old cities, is situated in the European part of the country, around 300km to the east of Moscow.

The most important industry and economic activities are mechanical engineering along with timber and textiles.

The location on the River Oka, a tributary of the Volga and thus an important waterway, as well as the good connections to important main roads and rail routes, are positive economic factors.

It is near Murom that German formwork and scaffolding specialist 298 PERI is providing a complete range of services for the construction of the three 90m high bridge piers.

Positioned at distances of 231m from each other respectively, these have been designed to carry the loads of the cable-stay construction which will span the River Oka at a height of 30m. The bridge is scheduled to be opened in 2009.

Underneath the carriageway, the cross-sectional form and dimensions of the pylon legs are continuously changing and the pentagonal basis transforms into a rectangle at height of the carriageway slab. In addition, the resulting outside pylon edges exhibits a curvature with a 300mm radius. From the top edge of the carriageway upwards, the shape and dimensions in a lateral direction remain constant for the most part; in a longitudinal direction, however, the external dimensions of the pylon tapers from 6-3m.

For the 21 concreting sections in each case, with 3.67m standard cycle heights, PERI engineers designed customised climbing formwork solutions and, in so doing, relied on the flexibility of the PERI VARIO girder wall formwork. In connection with workflow-oriented execution planning, all required adjustments can be carried out on the variable cross-sections from cycle to cycle with a minimum of time and effort. Together with the PERI CB climbing scaffold system for the vertical and slightly inclined areas as well as SKS/SSC brackets of the PERI SKS single-sided, retractable climbing formwork for the forward and reversed-angled sections, fully adaptable climbing formwork units are formed. On each of the pylon legs, the four scaffold platforms along with the re-adjusted formwork for each concreting section is climbed by means of a single crane pick.

"As a cost-effective solution for non-standard and unusual architect demands as well as any kind of special designs, PERI also delivers pre-assembled 3D formwork units directly to the construction site," says the company.

"For the Murom bridge, these serve to accurately form the contours of the pier geometry at the bottom, and are attached to the inside of the VARIO formwork at the front." The customised individual units were produced in Weissenhorn at the company's 866 CNC timber processing plant but then shipped to Russia in the form of compact construction kits.

"Due to the precision-made formed components complete with insertion slits, the clear markings and an exact construction plan, joining was able to be carried out on site with only a minimum of effort." The contractor is 2450 Mostotrest of Moscow, and field service is by PERI Moscow and Weissenhorn.

For more information on companies in this article

Related Content

  • PERI’s balancing act at the Harpe Bru Bridge in Norway
    May 24, 2016
    Plans for the European Route E6 expansion in Norway include the 320m-long Harpe Bru Bridge over the Gudbrandsdalen Lågen River, at Sør-Fron in Oppland province. For the superstructure, PERI civil engineering technology experts developed a balanced cantilevered solution based on the VARIOKIT Engineering Construction Kit. Statens vegvesen, Norway’s agency for public road building, selected an extradosed cable-stayed bridge design – the first such bridge in Norway. It combines the load-bearing behaviour
  • PERI fills gap in Greek market
    February 19, 2013
    A team of Greek and German PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece. The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arc
  • Forming iconic structures
    July 18, 2012
    Specially designed and constructed formwork is being used to create some iconic bridges worldwide The Golden Ears Bridge over the Fraser River will unite the municipalities of Richmond, New Westminister and Delta in the scenic British Columbia province of Canada. The bridge, part of a CAD$800 million (US$670 million) project, is an 'extra dosed' cable stayed bridge, which means the deck will be supported by both cables and the structure itself. This design reduces the overall height of the two towers as req
  • Pre-stressed bridge decks use modular formwork system
    July 9, 2012
    Imaginative formwork, often using modular components, is helping to shape some challenging bridges worldwide. Patrick Smith reports Traffic volumes in and around Prague have swollen massively in recent years, pushing the existing road network to the limits of its capacity. To permanently ease congestion in the Czech capital's centre, a multi-lane orbital motorway is under construction as a high capacity bypass for central Prague and to link up all the motorways and other major highways radiating from the ci