New bridge for old Russian city

Murom, one of Russia's best preserved old cities, is situated in the European part of the country, around 300km to the east of Moscow. The most important industry and economic activities are mechanical engineering along with timber and textiles. The location on the River Oka, a tributary of the Volga and thus an important waterway, as well as the good connections to important main roads and rail routes, are positive economic factors. It is near Murom that German formwork and scaffolding specialist PERI is p
July 30, 2012 Read time: 3 mins
Impressive: The cable-stay bridge over the River Oka features two 231m spans and is carried by three pylons with heights of around 90m. Photo: PERI
Murom, one of Russia's best preserved old cities, is situated in the European part of the country, around 300km to the east of Moscow.

The most important industry and economic activities are mechanical engineering along with timber and textiles.

The location on the River Oka, a tributary of the Volga and thus an important waterway, as well as the good connections to important main roads and rail routes, are positive economic factors.

It is near Murom that German formwork and scaffolding specialist 298 PERI is providing a complete range of services for the construction of the three 90m high bridge piers.

Positioned at distances of 231m from each other respectively, these have been designed to carry the loads of the cable-stay construction which will span the River Oka at a height of 30m. The bridge is scheduled to be opened in 2009.

Underneath the carriageway, the cross-sectional form and dimensions of the pylon legs are continuously changing and the pentagonal basis transforms into a rectangle at height of the carriageway slab. In addition, the resulting outside pylon edges exhibits a curvature with a 300mm radius. From the top edge of the carriageway upwards, the shape and dimensions in a lateral direction remain constant for the most part; in a longitudinal direction, however, the external dimensions of the pylon tapers from 6-3m.

For the 21 concreting sections in each case, with 3.67m standard cycle heights, PERI engineers designed customised climbing formwork solutions and, in so doing, relied on the flexibility of the PERI VARIO girder wall formwork. In connection with workflow-oriented execution planning, all required adjustments can be carried out on the variable cross-sections from cycle to cycle with a minimum of time and effort. Together with the PERI CB climbing scaffold system for the vertical and slightly inclined areas as well as SKS/SSC brackets of the PERI SKS single-sided, retractable climbing formwork for the forward and reversed-angled sections, fully adaptable climbing formwork units are formed. On each of the pylon legs, the four scaffold platforms along with the re-adjusted formwork for each concreting section is climbed by means of a single crane pick.

"As a cost-effective solution for non-standard and unusual architect demands as well as any kind of special designs, PERI also delivers pre-assembled 3D formwork units directly to the construction site," says the company.

"For the Murom bridge, these serve to accurately form the contours of the pier geometry at the bottom, and are attached to the inside of the VARIO formwork at the front." The customised individual units were produced in Weissenhorn at the company's 866 CNC timber processing plant but then shipped to Russia in the form of compact construction kits.

"Due to the precision-made formed components complete with insertion slits, the clear markings and an exact construction plan, joining was able to be carried out on site with only a minimum of effort." The contractor is 2450 Mostotrest of Moscow, and field service is by PERI Moscow and Weissenhorn.

For more information on companies in this article

Related Content

  • Safety upgrade for Canadian highway
    February 20, 2012
    New machines from Dynapac have played an important role in tackling a stretch of Canadian highway with safety issues. The machines have been used to meet experimental compaction standards specified by highway engineers, so as to withstand Canada's harsh winter conditions. Canadian contractors InterCite Construction and Pavex of St Felicien have used the new Dynapac machines for work on upgrading Route 175, one of Canada's most dangerous highways, located in the Province of Quebec. Route 175 is a 174km long
  • GPS machine control paves the way for Turkish canal
    February 7, 2012
    GPS machine control for earthworks and concrete paving is helping to fast track construction of an irrigation canal in Turkey - Claire Symes reports. The Turkish economy is expected to flourish as a result of construction of a new irrigation channel currently underway in the east of the country. This canal is benefiting from the latest concrete paving and earthmoving technology and will bring with it prosperity to a deprived area of the country. But the project is already taking the lead in terms of Turkish
  • Bridge design using flow modelling techniques
    February 17, 2012
    SBG has set numerous engineering precedents with its hugely innovative Jamarat Bridge project in Saudi Arabia
  • Delayed Houston Ship Canal Bridge nearing first phase
    February 23, 2024
    The delayed Houston Ship Canal Bridge is nearing its first phase completion.