Mobile grouting trailers for soil nail rigs

Geotechnical specialists, Bachy Soletanche and Carillion Piling are currently working on an £18 million (e21 million) geotechnical contract as part of carriageway improvements on the M1 motorway to the north of London, England. The work between junctions 10-13, Luton to Milton Keynes, is being carried out for the Costain Carillion joint venture working on behalf of the Highways Agency. The piling and soil nailing works are to facilitate the conversion of the current hard shoulder to a peak-time running lane
February 7, 2012 Read time: 3 mins
Geotechnical specialists, 1485 Bachy Soletanche and 2354 Carillion Piling are currently working on an £18 million (e21 million) geotechnical contract as part of carriageway improvements on the M1 motorway to the north of London, England.

The work between junctions 10-13, Luton to Milton Keynes, is being carried out for the Costain Carillion joint venture working on behalf of the Highways Agency.

The piling and soil nailing works are to facilitate the conversion of the current hard shoulder to a peak-time running lane with further junction improvements including 60 improved sign gantries and emergency refuges, over the 25km length.

Designed by the 2309 Highways Agency's engineer, Parsons Brinkerhoff, and Costain Carillion's engineer, Scott Wilson, there has been no need for additional land take.

The work is phased between the three junctions on only one carriageway at a time to avoid disruption to the travelling public and to abide by health and safety regulations.

Due to last up to 90 weeks, the project includes 250 Continuous Flight Auger (CFA) gantry piles each 750mm diameter and up to 20m long, with vibrated full-length reinforcement cages, 1600, 750mm diameter CFA piles for the contiguous bored pile walls up to 11m long in the emergency refuges, and 22,000 hollow stem and solid bar soil nails to stabilise the new cuttings and embankments, which are between 5m and 12m long.

The embankments are made up of a variety of fill materials, and the cutting slopes are generally within clay with flints over chalk (these achieve a maximum thickness of 5m and are thought to have originated from prolonged in situ weathering of outcrops of the Woolwich and Reading beds, while the chalk formation occurs as upper chalk, middle chalk, grey chalk and chalk marl along the length of the route).

The piling jv team said of the works: "High levels of safety have been paramount with this project due to working close to live traffic and some overhead power lines. This has led to a number of innovations by the Bachy Soletanche and Carillion Piling jv, including guarded soil nail rigs with a safe operator platform, improved guarding and auger cleaning for CFA piling, rope access systems, mobile grouting trailers, and a new Geoweb securing system. The new developments ensure work can be completed within the specified time frame with minimised safety risks."

For more information on companies in this article

Related Content

  • New safer road workzone practices
    September 15, 2014
    In the UK, the construction business Connect Plus Services is implementing new practices that reduce the need for crossings of live carriageways. These practices are expected to save the lives of road construction workers. Connect Plus Services is the company that has the contract to maintain, operate and upgrade the M25 motorway around London over a 30-year period. The contract is carried out on behalf of the Highways Agency. The firm has developed a new method of managing traffic approaching road construc
  • Upgrade work starts on junction of London’s orbital motorway M25
    February 20, 2015
    Work has started on a €136 million road improvement project on the UK’s London ring road, the M25 motorway. Crews from Balfour Beatty and Skanska have moved onto the interchange between the A13 national road and the M25 at junction 30 near Thurrock in the county Essex. The A13 on approach to the junction will be widened to four lanes in each direction and the junction itself will have dedicated link roads between the M25 and the A13. “Traffic at the junction is expected to grow by up to a quarter b
  • Goldhofer to a Faktor of 5
    January 3, 2013
    Goldhofer has launched its new Faktor 5 high girder bridges. The bridges, said by the German firm to allow the transport of up to five times their own weight, come in various models with deadweights ranging from 70 to 130tonnes, making it possible to transport payloads ranging from 350 to 650tonnes. Said by Goldhofer to be comfortable with transporting extremely heavy loads such as transformers, generators, or other heavy industrial components, the new high girder bridges have a vertical stroke in the loadi
  • Major project to construct landmark Bay Bridge in California
    October 31, 2012
    Iconic California crossing will offer seismic safety – Adrian Greeman reports A unique single-span single-tower suspension bridge is the iconic centrepiece of a dramatic renewal of the eastern Bay Bridge in California, crossing from San Francisco to Oakland. Tourists in San Francisco sometimes mix up their bridges, identifying as the famous Golden Gate, the double suspension bridge which runs across the wide San Francisco Bay. These serially linked bridges in fact form the Bay Bridge east to Oakland whereas