Engineering the Saadiyat Expressway

A new bridge, said to be the largest in the United Arab Emirates (UAE) in terms of area, is being constructed as part of a major highway project. The US$550 million Saadiyat Expressway project, which involves Leighton Construction (Abu Dhabi), related to one of Australia's largest contracting groups, in constructing a ten-lane, 6.5km long highway to link the UAE's main city, with an exclusive island lying just offshore.
February 24, 2012 Read time: 4 mins
The Saadiyat Expressway project in Abu Dhabi where RMD Kwikform supplied the formwork and falsework for all the structures
A new bridge, said to be the largest in the United Arab Emirates (UAE) in terms of area, is being constructed as part of a major highway project.

The US$550 million Saadiyat Expressway project, which involves Leighton Construction (Abu Dhabi), related to one of Australia's largest contracting groups, in constructing a ten-lane, 6.5km long highway to link the UAE's main city, with an exclusive island lying just offshore.

Conceived and driven by the Abu Dhabi Tourism Development and Investment Company, the arterial route, together with its interchanges, side roads and 1.6km of bridge decks, is scheduled to be complete in time for the inaugural Abu Dhabi Grand Prix (1 November, 2009), which could well decide the 2009 Formula One World Championship.

In January 319 RMD Kwikform Middle East's engineers started the design process to help contractor Leighton construct the eight in situ concrete box girder bridges and a tunnel required for the expressway.

Leighton Construction (Abu Dhabi) decided to award RMD Kwikform the contract to supply the formwork and falsework for all of the structures on this critical project as a result of the company's reputation and its ability to respond to a complex series of requirements.

These, says RMD, included having the flexibility of service to not only undertake all of the logistical planning and detailed design for each of the different locations, but also to offer the alternative of hire and purchase as appropriate to each application. While the vast majority of the equipment is being sold to Leighton Construction, the formwork for bridge B31 and all the top slab support along the 1.6 km of bridges will be rented.
At 180m long and 80m wide, the Golf Land Bridge will not only be the biggest bridge on the Saadiyat Island Expressway, but also the largest bridge  in terms of area built to date in the UAE.

Andy Teesdale, RMD Kwikform's contract manager for the area, remarks on the size of the project saying: "This is a massive undertaking, where we are working in partnership with Leighton Construction to offer the contractor the level of service essential to keep the reinforced concrete construction for all the structures on track.

"Aside from the fact that the work will see a staggering 215,000m³ of our Rapidshor falsework either purchased or hired to the client, our involvement also involves responsibility for design detailing and site safety. Programming of the work is critical for a lot of reasons, not least the seasonal variation in temperature: because it has such a dramatic effect on the rate at which the concrete hardens and gains strength.

"We normally design for an ambient temperature of 25°C, but this can drop to around 15°C in winter here, which slows the cure and could have potentially disastrous implications if we do not take account of the fact for the formwork design."

The decks to the bridges are all being designed as concrete box girders, with the 2m deep section being divided into a series of cells. The formwork has been planned and detailed so that the main elements can be pre-assembled on the ground, lifted into position and then moved again with as little adjustment as possible.

The most technically challenging requirement for RMD Kwikform to date has been the design and manufacture of special steel forms to cast the complex geometric shapes to a number of the pier heads.

These were fabricated from steel, not to enable high repetitions, but to cope with the very high concrete pressures and variations in profile.

Square on plan, the special shutters measure 2,800mm by 2,600 mm and have a double curvature. The design loading for these special steel forms means only four re-uses as the mix is poured, compacted and hardens.

For the 870m long tunnel that traverses the line of the main highway, once the base slab is laid, RMD Kwikform is to supply its Alform beams and Superslim soldiers to cast the walls. Then for the roof to the tunnel, the method of construction switches to the use of the specialist's table-forms. These will be assembled using RMD Kwikform's Alshor Plus system, making up 30m long sections, which can be struck and advanced as a single unit as soon as the concrete has gained sufficient strength. The cut-and-cover structure will then be backfilled.

Although at 27km², Saadiyat Island is only half the size of Bermuda, but is considered to represent one of the most important development opportunities in Abu Dhabi's history. The completion of the new expressway will help open up this natural idyll as an international tourism destination and residential centre.

For more information on companies in this article

Related Content

  • Norway’s record breaking undersea road tunnel
    February 25, 2015
    The world's deepest road tunnel is currently in construction near Stavanger in Norway but is only the prelude to even larger projects - report and photographs by Adrian Greeman. Norway's convoluted coastline of fjords and high mountains is famously scenic but also a major problem for transport and connections. The country has long experience of constructing tunnels as a result. Now a series of tunnels underway, or in design, around the oil industry city of Stavanger will stretch its skills more than usual.
  • New road project for Abu Dhabi
    December 13, 2017
    A new US$307.5 million highway project is now underway in Abu Dhabi, with completion expected in the second quarter of 2020. The project involves building a new road link from Umm Lafina and the Al Reem islands to the Sheikh Zayed bin Sultan Road. The work is being split into two separate contracts. One contract involves the construction of a 6.5km road connection from Al Reem Island and traversing Umm Lafina Island. This section will feature three lanes in either direction, as well as three bridges
  • India’s capital highway project will improve transport connections
    October 10, 2017
    Huge numbers of construction machines as well as plant and equipment are working overtime, backed by mammoth manpower, to meet the targeted completion deadline of March 2018 for India’s Eastern Peripheral Expressway (EPE). The 135km arterial route is being built with six lanes and surrounds India’s National Capital, Delhi, its National Capital Region (NCR) and the industrially developed North Indian states of Haryana and Uttar Pradesh.
  • Bids for the Construction of The New Abu Dhabi - Dubai Main Road
    April 23, 2012
    Contractors across the globe are being invited to bid for the contract to build the new main road between Abu Dhabi and Dubai. The Department of Transport (DoT) in Abu Dhabi says the E311 aims to alleviate traffic congestion on the current E11 main road connecting the two emirates. It will also create new entrances to the city of Abu Dhabi, Abu Dhabi International Airport, and Yas and Saadiyat Islands. The E311 project is one of the biggest infrastructure projects that Abu Dhabi DoT is working on as part of