A key section of the busy A12 route in Austria’s Tyrol area has been refurbished with help from formwork specialist Doka. The company devised a formwork traveller featuring steel panels so as to help build a new inner shell for the twin-tube Senftenberg Gallery tunnel. The job involved 36 pouring sections for work on the first tube followed by a break to accommodate winter tourist travel. After some minor modifications the same formwork traveller was then re-used for another pouring a further 36 sections on
January 4, 2017 Read time: 2 mins
Doka’s formwork has helped revamp a twin tube tunnel on Austria’s A12 highway
A key section of the busy A12 route in Austria’s Tyrol area has been refurbished with help from formwork specialist 203 Doka. The company devised a formwork traveller featuring steel panels so as to help build a new inner shell for the twin-tube Senftenberg Gallery tunnel. The job involved 36 pouring sections for work on the first tube followed by a break to accommodate winter tourist travel. After some minor modifications the same formwork traveller was then re-used for another pouring a further 36 sections on the second tube.

The job involved the renovation of the twin-tube highway tunnel with an existing centre wall and V-shaped columns. The 360m long tunnel sections are 10m wide by 6.5m high and the work was carried out by contractor 945 Strabag.

Formwork sheet made of steel panels was employed as this ensured a long lifespan and a high-grade concrete finish, allowing the pouring of 72 sections without replacing the panels. The formwork traveller met key requirements for the work and was pre-assembled by Doka, cutting costs for the contractor.

For more information on companies in this article

Related Content

  • Australian bridge slides into position
    July 18, 2012
    A heavy rail crossing as part of Australia's EastLink motorway demanded great ingenuity and careful planning Most of the 88 bridges on the EastLink tolled motorway in, Melbourne, Australia were kept as simple and straightforward as possible. Contractor Thiess John Holland (TJH) developed its own precast yard 150km from the city, which provided many of the prefabricated materials required for the structures. This offered speed and economy while logistics and sequencing were vital for their erection. But the
  • Giving four hours back to the day… and much more
    October 7, 2019
    A 20km long elevated expressway in Dhaka will be one of Bangladesh’s first Public Private Partnership transport projects – words and pictures by Ruby Kitching, on behalf of Mott MacDonald.
  • Concrete pumps speed busy road upgrade
    February 14, 2012
    WORK ON a major upgrade at a busy German road junction is expected to be completed by the end of 2011. To assist in the project, two Putzmeister large-boom concrete pumps, an M 58-5 from Berger Beton and an M 62-6 from BFM Betonförderdienst in Munich, arrived at the Neufahrn motorway junction, north of the city. The junction, when viewed from above, looks like a flatly pressed four-leaf clover, and can no longer cope with traffic volumes. Two national motorways, the A 9 and the A 92, intersect at the
  • Concrete pumps speed busy road upgrade
    May 3, 2012
    Work on a major upgrade at a busy German road junction is expected to be completed by the end of 2011. To assist in the project, two Putzmeister large-boom concrete pumps, an M 58-5 from Berger Beton and an M 62-6 from BFM Betonförderdienst in Munich, arrived at the Neufahrn motorway junction, north of the city.