Czech bridge sees world formwork debut

The Czech government is investing heavily in upgrading and modernising the country's top-tier transportation infrastructure. This year alone, building works with a total investment of over E1.6 billion are planned or underway on the Czech motorway and main road network. Completion of the D8 motorway between the Czech capital Prague and Dresden in the east of Germany has a high priority, and as part of this large-scale project, the contracting consortium of SMP and Metrostav is erecting the 585m long Prosmyk
July 23, 2012 Read time: 3 mins
The contracting consortium of SMP and Metrostav is erecting the motorway bridge over the River Elbe in the Czech Republic using the newly developed Doka cantilever forming traveller
The Czech government is investing heavily in upgrading and modernising the country's top-tier transportation infrastructure. This year alone, building works with a total investment of over E1.6 billion are planned or underway on the Czech motorway and main road network.

Completion of the D8 motorway between the Czech capital Prague and Dresden in the east of Germany has a high priority, and as part of this large-scale project, the contracting consortium of SMP and Metrostav is erecting the 585m long Prosmyky Bridge across the River Elbe.

Being built using the balanced cantilever method, the bridge is intended to relieve congestion on the existing old Elbe bridge and is scheduled to be opened for traffic in 2009.

This ambitious construction project marks the world debut for the newly-developed 203 Doka cantilever forming traveller.

Doka says that among the advantages of the rentable system are its modularity, which gives it maximum adaptability; its workplace-friendly design that uses optimised longitudinal trusses; an innovative drive concept using plastic slide bearings, and its standard of safety.

The Prosmyky Bridge spans the Elbe with a length of 585m, the box-girder superstructure resting on six piers, which are also being constructed using Doka Formwork Technology. The three spans of the superstructure are being cast by means of two Doka cantilever forming travellers in a total of 26 casting steps, each 15m wide and a maximum of 5m long. The widest span is 151m, giving the Prosmyky Bridge the longest span of any bridge in the Czech Republic.

Working outwards from a hammerhead, the segments are being poured and alternately post-tensioned on both sides of the piers. The cantilever forming traveller is fitted with Doka large-area formwork Top 50 elements. With sidewalls tapering from 7.5-3.5m; anchor blocks to be integrated in the middle of the carriageway slab; a quasi-hyperbolic radius of 325m, and the resulting change in the cross-section gradient from zero to 3.5%, the project makes some tough demands of the formwork solution, says Doka.

The Top 50 large-area formwork elements were delivered to the site by the Ceská Doka Ready-to-Use Service on a just-in-time (JIT) basis, pre-assembled with complete dimensional accuracy and ready for immediate use.

The cover-slab anchor blocks, positioned in the middle of the carriageway slab, present a particular challenge here, and the site crew is dealing with this by using specially made anchor-block box-outs, also fabricated by Ceská Doka's Ready-to-Use Service.

Doka's "innovative" cantilever forming traveller is dimensioned for casting 5m long bridge segments weighing up to 250tonnes, and this is sufficient to cover more than 90% of all balanced cantilever bridge projects anywhere in the world, says Doka.

"The Doka cantilever forming traveller's modular, flexible structure allows it to be used for forming straight, inclined and multi-cell box girder cross-sections without any time-wasting, cost-intensive modifications. It can also be used to form T-beams," says the company.

"As well as optimising the geometry and flexibility of the cantilever forming traveller by way of its modular structure, another main focus of the development effort, spread over several years, was on enhancing the workplace safety."

For more information on companies in this article

Related Content

  • Doka delivers on Kuwait's Nawaseeb Road
    May 11, 2021
    Along the 37km RA217 section of Nawaseeb Road poroject, Doka helped deliver Kuwait’s first in-situ cantilever bridge work.
  • Bridges in Sunderland and Poland are being slid into place
    February 6, 2017
    Sunderland sees a bridge slide into place and two bridges inch their way across a Polish highway Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation likely to take place next year. The project to build the New Wear Crossing is now halfway through with the first half of the steel deck b
  • Peri’s formwork and shoring solution for the “East End Crossing”
    July 6, 2016
    Pylons almost 90m high are a striking feature of a new cable-stayed East End Crossing bridge over the Ohio River in Louisville, Kentucky state in the US The pylons are characterised by their complex shapes and massive legs and cross beams. Peri provided a comprehensive overall concept for its construction – consisting of a planning solution with perfectly matched formwork, climbing, shoring and scaffolding systems along with extensive on-site support. With a Peri solution, the construction crew were a
  • Major bridge construction on Denmark's road project
    April 20, 2012
    Doka is playing a leading role in Denmark’s first ever public private partnership roadbuilding project. The 26km long, four-lane M51, 15km from the German border, will link Kliplev and Sønderborg in southern Jutland. And Doka will be the sole provider offormwork for the concrete used in erecting the motorway’s 72 bridges and crossings. The M51 is using 9000m² of the extremely adaptable Large-area formwork Top 50, and more than 4,750 basic frames of the heavyduty Load-bearing tower Staxo 100 system.