Curved girders for the Gaasperdammerweg A9 section in Amsterdam

Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of Ballast Nedam, Fluor, Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section
May 22, 2018 Read time: 3 mins
Curves galore: a little help from heavy transport and lifting specialist Sarens
Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam


It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of 8636 Ballast Nedam, 6343 Fluor, 1271 Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section of the Schiphol-Amsterdam-Almere road expansion.

IXAS Zuid-Oost’s responsibilities include design, build, management, maintenance and financing of the existing and new infrastructure of the A9 motorway between junctions Diemen and Holendrecht. Work includes the bridge over the river Gaasp, the road surface on the A9 Gaasperdammerweg and the construction of a 3km over-ground tunnel.

Value of the work is around €700 million, including a 20-year management and maintenance period after the new infrastructure becomes available. Ballast Nedam, Fluor, Heijmans and 3i Infrastructure are the sole shareholders in the project, with an equal share. Ballast Nedam, Fluor and Heijmans will participate in the construction and operation phase with an equal share of one third each.

Construction consortium IXAS decided that rather than replacing the horizontally curved structures, the consortium could widen them. This would minimise disruption to traffic and impact on the environment.

The consortium’s decision presented significant technical challenges to Haitsma Beton, a prefabricated concrete specialist. Haitsma Beton is now manufacturing nine major box-girders similarly horizontally curved to the ones on the bridge. These new additions are to be attached to the side of the flyover.

Haitsma Beton says that it is the first time that such a project has been attempted on horizontally curved flyovers in the Netherlands. The company, based in Kootstertille in the province of Friesland in the Netherlands, specialises in the production of precast piles and elements for bridges, viaducts, stadia, car parks and special construction projects, as well as concrete barriers. Haitsma Beton had previously supplied IXAS with the colossal prefabricated bridge girders for the new A9 bridges spanning the River Gaasp, which helped in the design of the new girders - seven for the northern bridge and two for the southern.

The new components are up to 26m long, 2.9m wide and weigh as much as 90,000kg. However, at only 900mm high, the girders are also extremely slender, which made incorporating the required amount of pre-stressed reinforcement an additional challenge, said Haitsma Beton.

Haitsma Beton achieved the required millimetre tolerances by continually monitoring the shape of the girders during construction and adjusting the tension of the reinforcing elements to control their camber. For aesthetic reasons, the outermost girders, which also form the edges of the bridge, are bevelled and will subsequently be provided with a boundary element.

Installation of the first girders started late last year. The remaining girders will be positioned during six weekend operations in which a portion of the road will always remain open to traffic. The last installation weekend is expected to take place in middle of this year.

“Despite its complexity, installation has so far run entirely to plan and the upward curvature of the girder is in perfect harmony with the contours of the existing deck,” says Jasper Doornbos, project manager at Haitsma Beton.

Work started in the last half of 2015 and the project, including a new tunnel, will be available for traffic fully in 2020.

For more information on companies in this article

Related Content

  • Bentley’s Be Inspired Awards highlight innovation in software use
    January 6, 2015
    Innovation, from design to on-site execution, is alive and well, thanks to a good helping of software application. David Arminas reports from software developer Bentley’s annual global conference, held this year in London Successful project delivery is increasingly about hard men and women using software to get the job done and this year’s global conference in London by US-based software developer Bentley highlighted some innovative - and startling - examples. As usual, the Year in Infrastructure 2014
  • I Lift NY crane places first girder on New York’s Tappan Zee Bridge
    June 25, 2015
    One of the world’s largest cranes has placed the first steel girder assembly for the approach span of the new NY Bridge, often called the Tappen Zee Bridge in New York. The barge-mounted I Lift NY super crane with its nearly 100m boom slowly picked up the 125m unit from its delivery barge and gently lowered it onto concrete pedestals in the Hudson River, near the Rockland County side of the bridge. The super crane will install even larger sections of the new bridge, some of which weigh around 907tonne
  • Storstrom Bridge to be Denmark’s third longest
    March 8, 2018
    Form and functionality come together in Denmark’s latest Storstrom Bridge design. David Arminas reports. An Italian joint venture recently won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate - Vejdirektoratet - awarded the work to a joint venture of Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 milli
  • Korean bridge construction poses challenges
    April 5, 2012
    On South Korea's southern coast, an innovative highway sea crossing is providing many engineering challenges The new Busan-Geoje crosses from South Korea's second city to its biggest island and is slightly shorter than the 12km of the country's famous Incheon project. In addition the main cable stay bridge for the Busan-Geoje project has a 475m span rather than the 800m of the Incheon central span. However the 8.2km Busan-Geoje project faces perhaps greater technical challenges and also includes a second b