Curved girders for the Gaasperdammerweg A9 section in Amsterdam

Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of Ballast Nedam, Fluor, Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section
May 22, 2018 Read time: 3 mins
Curves galore: a little help from heavy transport and lifting specialist Sarens
Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam


It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of 8636 Ballast Nedam, 6343 Fluor, 1271 Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section of the Schiphol-Amsterdam-Almere road expansion.

IXAS Zuid-Oost’s responsibilities include design, build, management, maintenance and financing of the existing and new infrastructure of the A9 motorway between junctions Diemen and Holendrecht. Work includes the bridge over the river Gaasp, the road surface on the A9 Gaasperdammerweg and the construction of a 3km over-ground tunnel.

Value of the work is around €700 million, including a 20-year management and maintenance period after the new infrastructure becomes available. Ballast Nedam, Fluor, Heijmans and 3i Infrastructure are the sole shareholders in the project, with an equal share. Ballast Nedam, Fluor and Heijmans will participate in the construction and operation phase with an equal share of one third each.

Construction consortium IXAS decided that rather than replacing the horizontally curved structures, the consortium could widen them. This would minimise disruption to traffic and impact on the environment.

The consortium’s decision presented significant technical challenges to Haitsma Beton, a prefabricated concrete specialist. Haitsma Beton is now manufacturing nine major box-girders similarly horizontally curved to the ones on the bridge. These new additions are to be attached to the side of the flyover.

Haitsma Beton says that it is the first time that such a project has been attempted on horizontally curved flyovers in the Netherlands. The company, based in Kootstertille in the province of Friesland in the Netherlands, specialises in the production of precast piles and elements for bridges, viaducts, stadia, car parks and special construction projects, as well as concrete barriers. Haitsma Beton had previously supplied IXAS with the colossal prefabricated bridge girders for the new A9 bridges spanning the River Gaasp, which helped in the design of the new girders - seven for the northern bridge and two for the southern.

The new components are up to 26m long, 2.9m wide and weigh as much as 90,000kg. However, at only 900mm high, the girders are also extremely slender, which made incorporating the required amount of pre-stressed reinforcement an additional challenge, said Haitsma Beton.

Haitsma Beton achieved the required millimetre tolerances by continually monitoring the shape of the girders during construction and adjusting the tension of the reinforcing elements to control their camber. For aesthetic reasons, the outermost girders, which also form the edges of the bridge, are bevelled and will subsequently be provided with a boundary element.

Installation of the first girders started late last year. The remaining girders will be positioned during six weekend operations in which a portion of the road will always remain open to traffic. The last installation weekend is expected to take place in middle of this year.

“Despite its complexity, installation has so far run entirely to plan and the upward curvature of the girder is in perfect harmony with the contours of the existing deck,” says Jasper Doornbos, project manager at Haitsma Beton.

Work started in the last half of 2015 and the project, including a new tunnel, will be available for traffic fully in 2020.

For more information on companies in this article

Related Content

  • Sunderland’s New Wear Crossing takes shape
    February 16, 2017
    The New Wear Crossing will be the first bridge to be built over the River Wear in Sunderland, UK, for more than 40 years Raising the bridge’s 100m-tall pylon promised to be a stunning visual sight, but also a tricky operation dictated by extremely variable local weather. World Highways went to press just before the operation, but not before the pylon had arrived by barge on January 7. It had completed a two-day crossing of the often unpredictable North Sea from the Belgian port of Ghent where it was f
  • First bridge deck section joined on UK’s Mersey Gateway project
    June 30, 2017
    The Mersey Gateway bridge project near Liverpool in England passed a milestone recently with the first joining of two of the deck sections.
  • Brisbane's highway of distinction
    August 2, 2012
    A massive AU$2 billion update of the Gateway Motorway in Queensland is underway to improve an infrastructure stretched by population boom. Report and photographs by Adrian Greeman Just 20 years after the Australian city of Brisbane built its Gateway Motorway with a high slim signature bridge dominating the river skyline, the road is being completely revamped. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels; the north is getting a completely
  • Cats eyes from Clearview set the tone at Switch Island in the UK
    February 23, 2018
    Cats eyes, which light up in response to changing traffic lights, will be used for the first time in the UK at a motorway junction. Highways England, the government agency, is installing around 170 of the LED road studs at Switch Island, one of England’s busiest motorway junctions – used by over 90,000 vehicles every day. Installation is expected to take around a year to complete.