Curved girders for the Gaasperdammerweg A9 section in Amsterdam

Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of Ballast Nedam, Fluor, Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section
May 22, 2018 Read time: 3 mins
Curves galore: a little help from heavy transport and lifting specialist Sarens
Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam


It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of 8636 Ballast Nedam, 6343 Fluor, 1271 Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section of the Schiphol-Amsterdam-Almere road expansion.

IXAS Zuid-Oost’s responsibilities include design, build, management, maintenance and financing of the existing and new infrastructure of the A9 motorway between junctions Diemen and Holendrecht. Work includes the bridge over the river Gaasp, the road surface on the A9 Gaasperdammerweg and the construction of a 3km over-ground tunnel.

Value of the work is around €700 million, including a 20-year management and maintenance period after the new infrastructure becomes available. Ballast Nedam, Fluor, Heijmans and 3i Infrastructure are the sole shareholders in the project, with an equal share. Ballast Nedam, Fluor and Heijmans will participate in the construction and operation phase with an equal share of one third each.

Construction consortium IXAS decided that rather than replacing the horizontally curved structures, the consortium could widen them. This would minimise disruption to traffic and impact on the environment.

The consortium’s decision presented significant technical challenges to Haitsma Beton, a prefabricated concrete specialist. Haitsma Beton is now manufacturing nine major box-girders similarly horizontally curved to the ones on the bridge. These new additions are to be attached to the side of the flyover.

Haitsma Beton says that it is the first time that such a project has been attempted on horizontally curved flyovers in the Netherlands. The company, based in Kootstertille in the province of Friesland in the Netherlands, specialises in the production of precast piles and elements for bridges, viaducts, stadia, car parks and special construction projects, as well as concrete barriers. Haitsma Beton had previously supplied IXAS with the colossal prefabricated bridge girders for the new A9 bridges spanning the River Gaasp, which helped in the design of the new girders - seven for the northern bridge and two for the southern.

The new components are up to 26m long, 2.9m wide and weigh as much as 90,000kg. However, at only 900mm high, the girders are also extremely slender, which made incorporating the required amount of pre-stressed reinforcement an additional challenge, said Haitsma Beton.

Haitsma Beton achieved the required millimetre tolerances by continually monitoring the shape of the girders during construction and adjusting the tension of the reinforcing elements to control their camber. For aesthetic reasons, the outermost girders, which also form the edges of the bridge, are bevelled and will subsequently be provided with a boundary element.

Installation of the first girders started late last year. The remaining girders will be positioned during six weekend operations in which a portion of the road will always remain open to traffic. The last installation weekend is expected to take place in middle of this year.

“Despite its complexity, installation has so far run entirely to plan and the upward curvature of the girder is in perfect harmony with the contours of the existing deck,” says Jasper Doornbos, project manager at Haitsma Beton.

Work started in the last half of 2015 and the project, including a new tunnel, will be available for traffic fully in 2020.

For more information on companies in this article

Related Content

  • Ballast Nedam, Deme and Macquarie win Blankenburgtunnel tender
    July 31, 2017
    Dutch construction company Ballast Nedam along with Belgian dredging company Deme and Australian investment bank Macquarie have won the Blankenburgtunnel tender in the Netherlands. The consortium - BAAK Blankenburg-Verbinding - will build the tunnel under the Nieuwe Waterweg river west of Vlaardingen, a city in southern Holland and on the north bank of the river Nieuwe Maas where it meets the Oude Maas.
  • Major highway widening project in Netherlands
    December 15, 2014
    A major highway widening and upgrade project is being carried out in the Netherlands in a bid to improve traffic flow on some of Europe’s busiest routes. SAAone is carrying out the work for the A1-A6 motorway project for Rijkswaterstaat, the Dutch Directorate-General for Public Works and Water Management. A key component of the project is adding new lanes to the A1 and A6 highways.
  • Netherlands highway stretch opens
    November 23, 2018
    The widened and upgraded A27/A1 highway stretches in the Netherlands have been officially opened to traffic. The upgraded highways connect Utrecht North and the Eemnes Junction, as well as the A1 highway between the Eemnes Junction and the Bunschoten-Spakenburg connection. The project was delivered two months ahead of schedule.
  • Effective precast barrier units from Netherlands firm
    April 29, 2015
    Haitsma Beton in the Netherlands has developed a lightweight precast concrete barrier system for temporary use. This T3 system is said to make investing in vehicle guidance more cost-effective. Each HaiSafe T barrier weighs 1.5tonnes and is over 10% lighter than comparable precast concrete barriers. The system is said to be easy and quick to locate, as well as to to assemble and disassemble. A novel feature is that no anchoring is needed at the ends, because the system has been tested and approved without a