Curved girders for the Gaasperdammerweg A9 section in Amsterdam

Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of Ballast Nedam, Fluor, Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section
May 22, 2018 Read time: 3 mins
Curves galore: a little help from heavy transport and lifting specialist Sarens
Dutch authorities recently needed to add traffic lanes to two flyovers at the Holendrecht junction on the Gaasperdammerweg section of the A9 motorway in Amsterdam


It was in November 2014 that the Directorate-General for Public Works and Water Management of the Netherlands Rijkswaterstaat awarded the A9 Gaasperdammerweg public-private-partnership project to IXAS Zuid-Oost, a consortium consisting of 8636 Ballast Nedam, 6343 Fluor, 1271 Heijmans and 3i Infrastructure. The A9 Gaasperdammerweg project is the third section of the Schiphol-Amsterdam-Almere road expansion.

IXAS Zuid-Oost’s responsibilities include design, build, management, maintenance and financing of the existing and new infrastructure of the A9 motorway between junctions Diemen and Holendrecht. Work includes the bridge over the river Gaasp, the road surface on the A9 Gaasperdammerweg and the construction of a 3km over-ground tunnel.

Value of the work is around €700 million, including a 20-year management and maintenance period after the new infrastructure becomes available. Ballast Nedam, Fluor, Heijmans and 3i Infrastructure are the sole shareholders in the project, with an equal share. Ballast Nedam, Fluor and Heijmans will participate in the construction and operation phase with an equal share of one third each.

Construction consortium IXAS decided that rather than replacing the horizontally curved structures, the consortium could widen them. This would minimise disruption to traffic and impact on the environment.

The consortium’s decision presented significant technical challenges to Haitsma Beton, a prefabricated concrete specialist. Haitsma Beton is now manufacturing nine major box-girders similarly horizontally curved to the ones on the bridge. These new additions are to be attached to the side of the flyover.

Haitsma Beton says that it is the first time that such a project has been attempted on horizontally curved flyovers in the Netherlands. The company, based in Kootstertille in the province of Friesland in the Netherlands, specialises in the production of precast piles and elements for bridges, viaducts, stadia, car parks and special construction projects, as well as concrete barriers. Haitsma Beton had previously supplied IXAS with the colossal prefabricated bridge girders for the new A9 bridges spanning the River Gaasp, which helped in the design of the new girders - seven for the northern bridge and two for the southern.

The new components are up to 26m long, 2.9m wide and weigh as much as 90,000kg. However, at only 900mm high, the girders are also extremely slender, which made incorporating the required amount of pre-stressed reinforcement an additional challenge, said Haitsma Beton.

Haitsma Beton achieved the required millimetre tolerances by continually monitoring the shape of the girders during construction and adjusting the tension of the reinforcing elements to control their camber. For aesthetic reasons, the outermost girders, which also form the edges of the bridge, are bevelled and will subsequently be provided with a boundary element.

Installation of the first girders started late last year. The remaining girders will be positioned during six weekend operations in which a portion of the road will always remain open to traffic. The last installation weekend is expected to take place in middle of this year.

“Despite its complexity, installation has so far run entirely to plan and the upward curvature of the girder is in perfect harmony with the contours of the existing deck,” says Jasper Doornbos, project manager at Haitsma Beton.

Work started in the last half of 2015 and the project, including a new tunnel, will be available for traffic fully in 2020.

For more information on companies in this article

Related Content

  • George Massey Tunnel Replacement gets environmental approval
    February 13, 2017
    The Canadian province of British Columbia has given environmental approval for a 10-lane US$2.8 billion bridge to replace the ageing George Massey Tunnel near Vancouver. However, approval for the 3km cable stay bridge over the Fraser River comes with 33 conditions, according to Canadian media. Construction of the toll bridge will also mean replacing the interchanges of Westminster Highway, Steveston Highway and Highway 17A.
  • PERI's tall order in Mexico
    February 14, 2012
    The Baluarte Bridge (Puente Baluarte), part of a major highway project, ranks among the most outstanding infrastructure projects ever constructed in Mexico.
  • Forming iconic structures
    July 18, 2012
    Specially designed and constructed formwork is being used to create some iconic bridges worldwide The Golden Ears Bridge over the Fraser River will unite the municipalities of Richmond, New Westminister and Delta in the scenic British Columbia province of Canada. The bridge, part of a CAD$800 million (US$670 million) project, is an 'extra dosed' cable stayed bridge, which means the deck will be supported by both cables and the structure itself. This design reduces the overall height of the two towers as req
  • BAM, PGGM and Habau win German A10-A24 contract
    December 20, 2017
    A consortium of BAM-PGGM and HABAU has been appointed preferred bidder for extension of Germany’s A10-A24 motorway from Neuruppin to Pankow, near Brandenburg. The public-private partnership deal covering nearly 65km is worth around €1 billion over the 30 years of the contract, according to infrastructure project management company DEGES.