Challenging tunnel conditions in Germany

Construction of the new German A44 route, linking the A7 near Kassel to the A4 near Herleshausen, is a challenging project.
June 30, 2020 Read time: 2 mins
The KEMROC cutter unit has been used to remove the temporary shotcrete layer at the Trimberg Tunnel

This includes the excavation of the 600m-long twin tube Trimberg Tunnel using conventional tunnelling methods. The tunnelling contractors at the HOCHTIEF/Züblin consortium had to contend with difficult geological conditions. Subsidence and loose boulders were encountered in both tunnel tubes for a length of 250m in the sandstone. For these reasons, the client, DEGES specified that the excavated tunnel should be stabilised using a temporary shotcrete layer.

Breakthrough of the North Tube of the Trimberg Tunnel took place in April 2019 and the contractor then started removing the temporary base layer.

A KEMROC DMW 130 cutter wheel mounted on a 23tonne excavator was used to remove the temporary structure. The concrete could be separated cleanly from the rock substrate and be recycled.

Using the KEMROC cutter has allowed efficient and accurate excavation
Using the KEMROC cutter has allowed efficient and accurate excavation

For the material removal work in the Trimberg Tunnel, a DMW cutting wheel rated at 130kW was chosen with 130mm cutting width and 600mm cutting depth. With this unit, the contractor achieved a cutting performance of 15-20m/hour. Using a cutter wheel also enabled the contractor to use an efficient removal process. The first step was to use the wheel to cut out a section, which was removed using a wheeled loader or excavator. The removed concrete was then taken off site by a waste disposal company as recycled material.

According to the consortium partners, a total of 125,000m3 of concrete has been removed from the two tunnel tubes in this tunnelling project. This has been carried out efficiently without a breaker, or drilling and blasting, saving costs.

For more information on companies in this article

Related Content

  • Cowi wins Massey Tunnel design
    July 22, 2022
    Cowi has won a contract as owner's engineer for an eight-lane replacement immersed tunnel under the Fraser River near the Pacific coast city of Vancouver. Cowi said it will draw on its experience designing the original four-lane George Massey Tunnel in 1959 and whose removal the engineering firm will later oversee.
  • E+ Screed Heating paves the way
    November 1, 2022
    The new E+ Screed Heating option by Volvo Construction Equipment (Volvo CE) allows customers to preheat screed on their pavers with less noise, less pollution and less hours at work.
  • Tough tunneling challenge in Italy
    May 25, 2016
    New levels of efficiency and sophistication are being seen in the latest earthmoving machines coming to market - Mike Woof writes. The earthmoving equipment segment accounts for one of the largest parts of the total market for construction machines. All around the world excavators and articulated dumptrucks (ADTs) can be seen operating on construction sites. With a massive array of manufacturers offering these machines, it is no surprise that the segment is hotly contested. In developed markets firms are en
  • Novel demolition machines
    May 9, 2023
    The market for ruggedised demolition excavators has very specific requirements, with three new models now available – Mike Woof writes