Building Norway's longest suspension bridge

AT 1.38KM LONG, the new €213 million Hardanger Bridge crossing Hardangerfjord, Norway's second largest fjord, will be the country's longest suspension bridge. The structure, designed by Norway's Forum Arkitekter, will be a new landmark with its 200m high concrete towers and steel construction.
March 2, 2012 Read time: 3 mins
Commanding position: one of three Liebherr 280EC-H16 Litronic tower cranes at Hardangerfjord
AT 1.38KM LONG, the new €213 million Hardanger Bridge crossing Hardangerfjord, Norway's second largest fjord, will be the country's longest suspension bridge. The structure, designed by Norway's 1206 Forum Arkitekter, will be a new landmark with its 200m high concrete towers and steel construction.

Work on the bridge in south-western Norway started earlier this year and is due for completion in 2013. An 800m road links the bridge with its associated 2.4km tunnel, and the bridge provides an important link, which will replace the existing ferry service between Brurvik and Brimnes. 1208 Statens Vegvesen, the Norwegian roads authority, has awarded the package for concrete works, including the towers, to 1209 Veidekke Entreprenør, and the steel deck and cable works to Danish contractor 1210 MT Hojgaard. The tunnels are being built by 1213 AF Skandinavia.

Veidekke Entreprenør is using three 718 Liebherr 280ECH16 Litronic tower cranes, supplied on rental by crane hire specialist 1214 E D Knutsen Maskin, to help build the bridge, which will have a main span of 1.31km, making it the seventh longest suspension bridge in the world. Because of the deep fjord, the towers are placed close to the shore and the short backspans lead directly into the new tunnel on the south side and an existing tunnel on the north side.

The maximum water depth near the bridge is some 500m and the surrounding mountains are up to 1,200m high, while the bridge will have a clearance above mean high water at mid-span of 55m The three Liebherr cranes were selected for their ease of erection in the difficult terrain and their high-load, fast-lift capacity. They can carry a maximum load of 16tonnes and at the full jib length of 70m can lift 3.1tonnes. Two of the cranes will be used for assembling the towers and will be fastened to the side of the structure, giving them an eventual 200m hook height.

The third crane, on the south side, will be used for lifting duties associated with the road, tollway system and the tunnel.

In total, over 14,000tonnes of steel will be used in the construction of the bridge (the suspension cables alone weigh 6,400tonnes). Assembly of the steel will be initiated in 2011, when the concrete pillars and the construction of roads and tunnels have been completed.

The bridge will be paid for by a combination of tolls, local and regional contributions and compensation for saved ferry costs/state funding, and when competed it will have two lanes for cars and one pedestrian lane, and will carry some 2,000 vehicles/day.

For more information on companies in this article

Related Content

  • First public outing for Liebherr tower crane at INTERMAT
    April 20, 2012
    Liebherr used INTERMAT 2012 to show its new 380 EC-B 16 Litronic flat-top crane. The 380tonne unit tops the 15-model range, which starts from 50tonnes. The new “flagship” can lift loads of up to 3,400kg at its 75m maximum radius. With the Litronic system, the 380 EC-B 16 can provide up to 20% more load lift at the push of a button. This is achieved by integrating the load-moment limiting system, the ABB operating-range limiting system and the MDA machine data evaluation program.
  • Liebherr tower cranes operating at Santiago airport
    January 14, 2019
    the Santiago Nueva Pudahuel International airport development is benefiting from the proximity of Liebherr’s branch location in Chile. At the moment, 18 of the 23 Liebherr tower cranes are in operation on the large-scale construction site. Of the machines in use, three are high-top models and 15 are flat-top types. The airport in Santiago de Chile is expanding its position as a key hub airport for South America. The operators are extending the site to 265,000m² and have commissioned the construction of a
  • Norway moves toward more E39 coastal road improvements
    April 4, 2019
    Norway is working on plans to make more of the major north-south E39 coastal route a ferry-free highway, coasting €35.3 billion, according to media. In Norway, the trans-European route 39 is part national road system and is developed and maintained by the public roads administration. It runs for 1,330km along the coast from Klett just south of Trondheim to Nørresundby. Norway’s E39 is mostly a two-lane undivided road with only relatively short sections near Stavanger, Trondheim and Bergen being motorw
  • Key highway project for Norway
    January 9, 2014
    The Norwegian Public Roads Administration, Statens Vegvesen , has awarded contracts for the E6 highway to Implenia and KA Austad and for the E18 south of capital Oslo. The E6 contract relates to the stretch connecting Vinstra and Sjoa in Gudbrandsdalen and is worth some €185.71 million. The construction work is now commencing and will take until October 2016 to complete. The project is for 16km of the E6 however it will include tunnel construction work. Hard, competent rock conditions mean that drill and bl