Bridge uses new forming carriage

The Holzmatttal Bridge for the A98 autobahn in southern Germany stretches 410m across the valley, and on this build the newly-developed Doka forming carriage TU is said to have demonstrated precisely how it drives progress with extremely short cycle times and speedy forming and stripping out operations. The underslung carriage also permits unobstructed access for site traffic.
February 7, 2012 Read time: 3 mins
The underslung Doka forming carriage TU is said to offer fast cycle times and a high safety standard for the construction or repair of bridge edge beam caps
The Holzmatttal Bridge for the A98 autobahn in southern Germany stretches 410m across the valley, and on this build the newly-developed 203 Doka forming carriage TU is said to have demonstrated precisely how it drives progress with extremely short cycle times and speedy forming and stripping out operations. The underslung carriage also permits unobstructed access for site traffic.

The incremental launching method was used for the bridge, which was recently completed between the towns of Lörrach and Rheinfelden.

Its piers are up to 30m high and the prestressed concrete superstructure was carried across in a total of 17 launch steps. The edge cap dimensions are 30cm wide and 55cm high and the centre cap is only slightly smaller.

The TU forming carriage, which was launched at Bauma 2010, was used for both.

"The TU is an underslung carriage and since it is designed specifically for forming edge caps and centre caps on bridge superstructures it contributes significantly to optimisation of the construction process," says Doka.

"The entire carriage is slung underneath the superstructure, so the various steps in the construction process are easily separated. Sealing work and the job of casting the bridge edge beam can be tackled simultaneously boosting, for example, efficiency at a key phase in construction.

"In much the same way, an underslung carriage makes placing the reinforcement and pouring the concrete far easier. This solution dispenses with the ballast sleds plus rails that a top-riding edge-beam forming carriage inevitably requires. When it comes to repairing bridge edge beam caps this is a crunch factor, because the work can proceed without significant disruption of traffic crossing the bridge." It took nine weeks to finish the edge cap with three steps concreted per week, and according to Doka the key to this speedy progress is the innovative suspension system that carries the underslung forming carriage TU.

"Installation and removal of the two-part hangers are speedy, safe operations undertaken from the leading and trailing platforms respectively." Each platform is 2.9m long and the integral adjuster mechanism is designed for maximum versatility, so the hanger adjusts easily in all three dimensions to compensate for the inevitable slight geometrical irregularities of the superstructure. The bogey unit of the TU has side-mounted guide rollers so it can track round curves without time-consuming stoppages for repositioning. An integral, self-latching gravity brake secures the forming carriage, preventing uncontrolled movement. Fully enclosed and preassembled working platforms round off the safety package and ensure maximum safety for the crew throughout every phase of the build.

 The TU is "design-perfect for speed in the forming and stripping out processes," with a special pivot mechanism enabling simultaneous horizontal and vertical movement: forming up and stripping out are involve a minimum number of steps.

Like Doka's Top 50 beam formwork, the TU was preassembled by the Doka Ready-to-Use Service and taken to site ready-to-go. The forming carriage arrived broken down into six units each 4m long, and they were fitted together under the professional eye of an experienced Doka site foreman.

For more information on companies in this article

Related Content

  • The Mersey Gateway bridge project continues on schedule
    October 18, 2016
    Work continues on the 2.3km Mersey Gateway signature bridge project close to Liverpool in the UK. David Arminas reports on some of the construction highlights. Under construction is a cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool. Including the approach viaducts on each side, it will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will b
  • PERI fills gap in Greek market
    February 19, 2013
    A team of Greek and German PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece. The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arc
  • Nigeria’s giant city Lagos to benefit from a new cable-stayed bridge
    September 19, 2012
    The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012. Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.
  • Challenging viaduct construction
    March 2, 2012
    TRAFFIC VOLUMES on Gran Canaria, the third largest of the Canary Islands, have been swelling rapidly in recent years, not least because of the boom in tourism. Among the routes most affected is the 32km long northern motorway GC-2 between Las Palmas and Agaëte, which has reached the limits of its capacity.