Bold move aids Ironton-Russell bridge works in U.S.

The bold decision to go against the norm and build the back spans using falsework for the Ironton-Russell replacement bridge between Parkersburg, Kentucky and Cincinnati, Ohio allowed land access to build the main span which, along with the first use in the U.S. of precast stay anchor blocks, meant the new structure could get built.
January 24, 2014 Read time: 3 mins
The bold decision to go against the norm and build the back spans using falsework for the Ironton-Russell replacement bridge between Parkersburg, Kentucky and Cincinnati, Ohio allowed land access to build the main Span which, along with the first use in the US of precast stay anchor blocks, meant the new structure could get built.

5978 Brayman Construction Corporation’s project works bid, utilising a combination of Brayman and 5979 Finley Engineering Group’s design and construction method changes, was 4% below Ohio State’s final cost estimate of US$84.6 million.

When Rich Blankenship became the mayor of the city of Ironton, he made it a priority to get this critical infrastructure project under way by working diligently with the Ohio Department of Transportation (ODOT), former Governor Ted Strickland, and current Ohio Governor John R. Kasich.

Opened in 1922, the original Ironton-Russell Bridge was the first highway bridge along the Ohio River between Parkersburg and Cincinnati. The cantilever bridge was retrofitted in 1970s, and later posted with restrictions, having become inefficient for today’s traffic and economically impractical to maintain. In 2000, ODOT recommended full replacement.

URS was selected in January 2006 to redesign the replacement bridge after ODOT rejected the bids of the initial single-tower, two-Span cable-stayed design, which came in well over construction estimates.

The new cable-stayed replacement bridge is a three-Span, two-tower design with two 3.65m travel lanes. The 797.35m long bridge is comprised of a 274.32m cable-stayed main Span and two 112.77m cable-stayed side spans, two 96.01m tall towers and two anchor piers on the river’s edge. The entire structure is cast-in-place with reinforced concrete featuring  2,630tonnes of rebar, utilising the cable stays to construct the bridge by the balanced cantilever methodology. Foundation units consist of 53 large-diameter drilled shafts ranging in size from 1.06m to 2.43m.

ODOT asked URS to oversee the revised portions of the design and construction that the Brayman-Finley team proposed. “The changes uphold the integrity of the original design, and, since some members were designed to support heavy construction equipment, the bridge has more robust side spans,” said Steve Stroh, URS’ project manager.

“Our early collaboration with Finley and VSL enabled us to work out alternative construction sequence solutions that ultimately saved ODOT $15.2 million over the next closest bidder,” said Stephen M. Muck, Brayman’s CEO.

Craig Finley Jr, managing principal of Finley, said, “The falsework was designed as a modular system, allowing it to be used for both the Kentucky and Ohio approaches and reducing the number of travellers from two to one."

For more information on companies in this article

Related Content

  • IRF awards Parsons for its East End Crossing work in the US
    August 7, 2015
    The International Road Federation (IRF) has awarded its Global Road Achievement Award for project finance and economics to Parsons for the East End Crossing of the Ohio River Bridges Project. Parsons, which served as the technical advisor for the implementation of a public-private partnership (PPP), received the award for achievements in cost savings and accelerated project delivery. This was done through the PPP procurement process for the development, design, construction, financing, operation and m
  • New bridge under construction in Turkey
    March 28, 2014
    Work is underway on a new bridge structure in Turkey, with tower cranes playing a key role in the project The two Potain tower cranes are being used to build a 610m long cable-stayed bridge in the south-east of the country. The two cranes are MC235B models and are working 10 hours/day on the project, which is taking 30 months. The new bridge will provide an important connection across the Ataturk Dam Reservoir on the Euphrates River.
  • São Paulo's landmark bridge construction
    February 21, 2012
    To improve access from the east to São Paulo city centre, main contractor Construbase Engenharia is building a road complex comprising three viaducts and access ramps. The greatest challenge in Brazil's largest city is the showpiece Padre Adelino viaduct, a 122m long single-arch, single-span, cable-stayed concrete bridge moulded in situ with a parabola-shaped arch and a single-cell post-tensioned cantilever caisson
  • International firms compete in US bridge project tenders
    May 2, 2012
    The Spanish construction firm ACS is tendering for the construction and operation of four bridges in the US. The firm is tendering in partnership with some other US and international firms for some of the projects, which are worth a total of US$11.4 billion. The Tappan Zee project is expected to cost $5 billion and the deal will be for a design and construction contract. The bridge will be located in New York, is being developed by New York State Thruway Authority and will require two, four-carriageway brid