BAUER mobilises rigs for UK’s A19/A1058 coast road piling works

In north-east England, work is underway to create an improved A19/A1058 Coast Road junction. The £75m scheme in the city of Newcastle involves the upgrade of a roundabout to an ambitious three-level interchange. The Sisk Lagan joint venture, the main contractor, called upon Bauer Technologies, to complete the piling works for critical structures. Bauer’s parent company, Bauer Spezialtiefbau, is a global construction company specialising in complex and specialist foundation works, with its head office in
April 10, 2017 Read time: 2 mins
Bauer Technologies is installing 583 contiguous rotary bored piles with diameters ranging from 600-1500mm.
In north-east England, work is underway to create an improved A19/A1058 Coast Road junction. The £75m scheme in the city of Newcastle involves the upgrade of a roundabout to an ambitious three-level interchange.

The Sisk 2340 Lagan joint venture, the main contractor, called upon 8350 Bauer Technologies, to complete the piling works for critical structures. Bauer’s parent company, Bauer Spezialtiefbau, is a global construction company specialising in complex and specialist foundation works, with its head office in Schrobenhausen, Germany.

Bauer’s scope of works is to install 583 contiguous rotary bored piles with diameters ranging from 600-1500mm. The piles, up to 31m long, are founded in sandstone bedrock to form contiguous pile walls, creating the trough for the future A19 “dive-under”. A number of the retaining wall piles also act as hybrid design elements by carrying the load of three major single-span bridges across the underpass. In order to verify the capacity of these critical foundations, Bauer will carry out three permanent pile load tests using the innovative Osterberg method.

The project is particularly challenging because it entails working within a major roundabout with a heavy volume of traffic, according to Martin Blower, managing director of Bauer Technologies.

In order to manage associated risks efficiently, Bauer is working closely with the joint venture and 8100 Highways England – the government agency - to implement stringent health and safety processes. In addition, Bauer said that it is “enthusiastically participating” in Highways England’s “Raising the Bar” scheme designed to raise standards in working efficiencies and quality of workmanship, as well as health and safety.

Piling works started in December 2016, with mobilisation of a Bauer BG30 rig, which will be followed by a second machine in early 2017. Piling works will be carried out in two phases and are expected to be complete by the end of this year.

For more information on companies in this article

Related Content

  • Cleveland Bridge on A1 project in the UK
    February 7, 2017
    Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges. Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge. The work was carried out on behalf of Highways England’s principal contractor on the A1 scheme, a Carillion and Morgan Sindall joint venture. The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorw
  • Bauer records high group revenue growth for Q3 at 22%
    November 15, 2017
    Bauer, equipment maker for ground investigation work, reports third quarter 2017 total group revenue up 22% on the previous year to just over €1,398 million. The German company said sales revenues increased by 27.5% to €1,265.6 million. However, the order backlog was €977.3 million that, while still high, was down from €1,019.0 million the previous year. This was due to a high double-digit million order backlog taken off the books after the sale of shares in a real estate company at the end of 2016.
  • Advances in concrete paving materials
    July 9, 2012
    Innovations in materials technology, as well as machines, could provide a major boost to the concrete paving sector - Mike Woof reports Development of new material technologies for the concrete paving sector continues apace and the latest innovations could provide the biggest boost for this market in many years. High performance cementitious material (HPCM) is an innovative concept that has been developed and tested for road surfacing applications as part of a project in which the UK's Transport Research La
  • The world’s longest suspension bridge
    June 24, 2024
    The world’s longest suspension bridge is the 1915 Çanakkale Bridge in Turkey. This engineering marvel links Gelibolu with Lapseki, forming a key section of the 101km highway linking Malkara with Çanakkale. *Article produced in partnership with the General Directorate of Highways (KGM), Ministry of Transport and Infrastructure, Republic of Türkiye.