BAUER mobilises rigs for UK’s A19/A1058 coast road piling works

In north-east England, work is underway to create an improved A19/A1058 Coast Road junction. The £75m scheme in the city of Newcastle involves the upgrade of a roundabout to an ambitious three-level interchange. The Sisk Lagan joint venture, the main contractor, called upon Bauer Technologies, to complete the piling works for critical structures. Bauer’s parent company, Bauer Spezialtiefbau, is a global construction company specialising in complex and specialist foundation works, with its head office in
April 10, 2017 Read time: 2 mins
Bauer Technologies is installing 583 contiguous rotary bored piles with diameters ranging from 600-1500mm.
In north-east England, work is underway to create an improved A19/A1058 Coast Road junction. The £75m scheme in the city of Newcastle involves the upgrade of a roundabout to an ambitious three-level interchange.

The Sisk 2340 Lagan joint venture, the main contractor, called upon 8350 Bauer Technologies, to complete the piling works for critical structures. Bauer’s parent company, Bauer Spezialtiefbau, is a global construction company specialising in complex and specialist foundation works, with its head office in Schrobenhausen, Germany.

Bauer’s scope of works is to install 583 contiguous rotary bored piles with diameters ranging from 600-1500mm. The piles, up to 31m long, are founded in sandstone bedrock to form contiguous pile walls, creating the trough for the future A19 “dive-under”. A number of the retaining wall piles also act as hybrid design elements by carrying the load of three major single-span bridges across the underpass. In order to verify the capacity of these critical foundations, Bauer will carry out three permanent pile load tests using the innovative Osterberg method.

The project is particularly challenging because it entails working within a major roundabout with a heavy volume of traffic, according to Martin Blower, managing director of Bauer Technologies.

In order to manage associated risks efficiently, Bauer is working closely with the joint venture and 8100 Highways England – the government agency - to implement stringent health and safety processes. In addition, Bauer said that it is “enthusiastically participating” in Highways England’s “Raising the Bar” scheme designed to raise standards in working efficiencies and quality of workmanship, as well as health and safety.

Piling works started in December 2016, with mobilisation of a Bauer BG30 rig, which will be followed by a second machine in early 2017. Piling works will be carried out in two phases and are expected to be complete by the end of this year.

For more information on companies in this article

Related Content

  • Bauer’s new piling machine models
    November 29, 2018
    Bauer is offering new piling rigs, including models developed for the Chinese market needs. According to general manager Michael Minsky, the new GB80S is an improved version of the earlier GB60 model. He said “We did an upgrade and made it stronger and more productive.” The BCS40 is built specifically for the Chinese market. Although sharing the same build quality as the premium machines, it comes with fewer options and is priced to compete on closer levels to locally made equipment. The base of the machin
  • GEWI piles for Blankenburg Connection
    June 17, 2020
    BAUER Funderingstechniek is installing GEWI micropiles with threads as part of Rotterdam’s new 4km-long A24 highway that includes two tunnels under the Scheur River
  • Kier rebuilds storm-damaged road in England’s tourist Cumbria region
    May 10, 2016
    The first of 20 steel posts have been positioned for major road repairs to the A591 road in northern England under a £40 million project to repair December storm damage. The A591 is a major local authority road in Cumbria. It links the M6 motorway near Brettargh Holt with important Lake District tourist destinations such as Kendal, Windermere, Ambleside, Grasmere and Keswick.
  • Soilmec’s compact piling rig works in tight spots
    February 2, 2015
    Italian drilling, piling and foundation equipment specialist Soilmec is introducing its compact SM-4 rig designed to create sectional flight auger (SFA) piles, a technique that uses sectional lengths of a hollow stem continuous flight auger. Soilmec says that the new machine is ideal for “job sites with low head room or very restricted (access),” and in situations that “a CFA rig cannot reach.” Once the SM-4 is on site, “each section, commencing with a toothed lead auger, is added to the rig as the auger