Geotechnical specialists Bachy Soletanche has started work on a new grade separated interchange on the A41 road in West Bromwich in the English Midlands for a Balfour Beatty/Birse joint venture.
      
  
           
                          
                February 7, 2012
              
            
                          
                Read time: 1 min
              
                    
                 
    Geotechnical specialists 1485   Bachy Soletanche has started work on a new grade separated interchange on the A41 road in West Bromwich in the English Midlands for a 1146   Balfour Beatty/1486   Birse joint venture.
 
Worth about.£2.5 million (e2.9 million) the project consists of heavy duty CFA and cased CFA secant piling.
 
The hard/hard and hard/firm secant CFA piles are 600, 750 and 900mm in diameter and up to 18.5m deep, and were designed by Sandwell Metropolitan Borough Council's engineer, Scott Wilson, and include reinforced primary piles in the new overbridges wing walls.
 
Bachy Soletanche's biggest rig, a BG40, is being used for the cased CFA secant piles with the remainder being installed by a CM70. Once complete, the retaining walls will form the new underpass beneath the newly-aligned roundabout so as to improve traffic flow on the A41.
 
Paul Hodgson, business development manager at Bachy Soletanche, said: "This is our biggest job in the Midlands at the moment and it's crucial we stick to schedule so as little disruption occurs as possible."
      
    Worth about.£2.5 million (e2.9 million) the project consists of heavy duty CFA and cased CFA secant piling.
The hard/hard and hard/firm secant CFA piles are 600, 750 and 900mm in diameter and up to 18.5m deep, and were designed by Sandwell Metropolitan Borough Council's engineer, Scott Wilson, and include reinforced primary piles in the new overbridges wing walls.
Bachy Soletanche's biggest rig, a BG40, is being used for the cased CFA secant piles with the remainder being installed by a CM70. Once complete, the retaining walls will form the new underpass beneath the newly-aligned roundabout so as to improve traffic flow on the A41.
Paul Hodgson, business development manager at Bachy Soletanche, said: "This is our biggest job in the Midlands at the moment and it's crucial we stick to schedule so as little disruption occurs as possible."
 
     
         
         
        