Arched bridge challenge over the Oparno

For environmental reasons planners decided in favour of the challenging task of constructing a 13-field arched highway bridge over the Oparno Valley in the Bohemian area of the Czech Republic. The 258m bridge, whose reinforced concrete arch has a span of 135m, straddles the valley without any bridge piers, transferring the loads in the form of compressive forces into the foundations.
February 29, 2012 Read time: 3 mins
The 258m long and 50m high arched bridge crosses the Oparno Valley in the Bohemian Forest. (Photo: PERI GmbH)
For environmental reasons planners decided in favour of the challenging task of constructing a 13-field arched highway bridge over the Oparno Valley in the Bohemian area of the Czech Republic.

The 258m bridge, whose reinforced concrete arch has a span of 135m, straddles the valley without any bridge piers, transferring the loads in the form of compressive forces into the foundations.

Known as the A17 in Germany and D8 in the Czech Republic, the highway connects Dresden and Prague. This in turn is part of the pan-European corridor which extends to Budapest (Hungary) and then on to Istanbul (Turkey). In the Bohemian Forest section alone, between Rehlovice and Lovosice, three interchanges, two tunnels and a total of 29 bridges are being constructed along the 16km route.

As most of the stretch of highway currently under construction passes through a landscape conservation area, special requirements due to strict environmental protection regulations have to be met by both the planners and contractor for the realisation of this particular highway section.

With the help of a comprehensive 298 PERI formwork and scaffolding solution, two separate parallel structures are concurrently being constructed in both driving directions.

In close cooperation with the Prague-based building contractor Metrostav, PERI developed a cost-effective all-in-one solution using a standardised modular system with mostly rentable system components for the construction of the bridge elements. For the Oparno Bridge, the VARIOKIT engineering construction kit; RCS rail climbing system as well as PERI UP modular scaffold all played a key role. Construction of the supporting structures has been "very economical, optimally adapted to the individual project requirements."

The reinforced concrete arch is being constructed with the help of two customised formwork and scaffolding units in the form of a cantilevered construction. With this, the fresh concrete loads of the 5-6m long arched sections are transferred into the previously completed load-bearing sections.

During the moving procedure, hydraulic units provide the required lifting power so that work can be carried out without crane support, to a large extent, regardless of the weather.

The 53m formwork carriage and the formwork system itself are optimally configured to form a homogeneous supporting structure. For moving around the piers, the formwork is simply folded downwards. Mobile hydraulic pumps, which also ensure that the PERI RCS rail climbing system can operate crane-independently, allow the striking and shuttering procedures to take place.

The RCS rail climbing system for the erection of the bridge piers supplement the customised PERI modular system concept for the Oparno Bridge. The bridge piers are constructed in concreting cycle heights of between 3.1-3.6m with RCS climbing units. PERI UP stairs and access ladders as well as working platforms serve to allow personnel to reach and assemble the temporary bracing for the arched supporting structure.

For more information on companies in this article

Related Content

  • New methods allow concrete testing on the spot
    July 20, 2015
    This month we look at two new methods which are allowing concrete to be tested on the spot, and [over the page] we catch up on the latest news from concrete testing equipment suppliers - Kristina Smith writes Sometimes test results can be very bad news. If the concrete pavement or bridge abutment has already been poured, and if the concrete does not meet the specification, the outcome could be very expensive remedial work.
  • Toggenburger takes two Terex cranes to tackle a Swiss tandem lift
    August 21, 2015
    Two of the largest cranes in Switzerland recently were called upon to lift an 884tonne, 162m-long connecting bridge between two buildings at the Coop distribution centre in Schafisheim. “The individual bridge components had enormous gross weights of up to 275tonnes and required us to use working radii of up to 29m,” said Andre Huber, project manager at Toggenburger, the company that took on the task. To get the job done, Toggenburger rolled out its biggest machinery which also happen to be the two lar
  • India’s capital highway project will improve transport connections
    October 10, 2017
    Huge numbers of construction machines as well as plant and equipment are working overtime, backed by mammoth manpower, to meet the targeted completion deadline of March 2018 for India’s Eastern Peripheral Expressway (EPE). The 135km arterial route is being built with six lanes and surrounds India’s National Capital, Delhi, its National Capital Region (NCR) and the industrially developed North Indian states of Haryana and Uttar Pradesh.
  • Peri UK celebrates 25 years at Rugby HQ
    October 23, 2023

    Formwork and scaffolding specialist Peri opened its depot in Rugby, northern England, in 1998 – 25 years ago. It immediately became home to a large inventory of the company’s products available for sale or hire to customers seeking safe, innovative and optimal temporary works systems for their construction projects.