Arched bridge challenge over the Oparno

For environmental reasons planners decided in favour of the challenging task of constructing a 13-field arched highway bridge over the Oparno Valley in the Bohemian area of the Czech Republic. The 258m bridge, whose reinforced concrete arch has a span of 135m, straddles the valley without any bridge piers, transferring the loads in the form of compressive forces into the foundations.
February 29, 2012 Read time: 3 mins
The 258m long and 50m high arched bridge crosses the Oparno Valley in the Bohemian Forest. (Photo: PERI GmbH)
For environmental reasons planners decided in favour of the challenging task of constructing a 13-field arched highway bridge over the Oparno Valley in the Bohemian area of the Czech Republic.

The 258m bridge, whose reinforced concrete arch has a span of 135m, straddles the valley without any bridge piers, transferring the loads in the form of compressive forces into the foundations.

Known as the A17 in Germany and D8 in the Czech Republic, the highway connects Dresden and Prague. This in turn is part of the pan-European corridor which extends to Budapest (Hungary) and then on to Istanbul (Turkey). In the Bohemian Forest section alone, between Rehlovice and Lovosice, three interchanges, two tunnels and a total of 29 bridges are being constructed along the 16km route.

As most of the stretch of highway currently under construction passes through a landscape conservation area, special requirements due to strict environmental protection regulations have to be met by both the planners and contractor for the realisation of this particular highway section.

With the help of a comprehensive 298 PERI formwork and scaffolding solution, two separate parallel structures are concurrently being constructed in both driving directions.

In close cooperation with the Prague-based building contractor Metrostav, PERI developed a cost-effective all-in-one solution using a standardised modular system with mostly rentable system components for the construction of the bridge elements. For the Oparno Bridge, the VARIOKIT engineering construction kit; RCS rail climbing system as well as PERI UP modular scaffold all played a key role. Construction of the supporting structures has been "very economical, optimally adapted to the individual project requirements."

The reinforced concrete arch is being constructed with the help of two customised formwork and scaffolding units in the form of a cantilevered construction. With this, the fresh concrete loads of the 5-6m long arched sections are transferred into the previously completed load-bearing sections.

During the moving procedure, hydraulic units provide the required lifting power so that work can be carried out without crane support, to a large extent, regardless of the weather.

The 53m formwork carriage and the formwork system itself are optimally configured to form a homogeneous supporting structure. For moving around the piers, the formwork is simply folded downwards. Mobile hydraulic pumps, which also ensure that the PERI RCS rail climbing system can operate crane-independently, allow the striking and shuttering procedures to take place.

The RCS rail climbing system for the erection of the bridge piers supplement the customised PERI modular system concept for the Oparno Bridge. The bridge piers are constructed in concreting cycle heights of between 3.1-3.6m with RCS climbing units. PERI UP stairs and access ladders as well as working platforms serve to allow personnel to reach and assemble the temporary bracing for the arched supporting structure.

For more information on companies in this article

Related Content

  • Almost gone: Canada’s old Port Mann Bridge deconstructed
    August 14, 2015
    Three years ago a welder’s cut halved Canada’s old Port Mann Bridge. David Arminas reports from the banks of the Fraser River. By the time this issue of World Highways reaches you, one of Canada’s iconic steel arch bridges will be a shadow of its former self. It’s been a three-year demolition job since the first cut across the deck of the old Port Mann Bridge just outside the city of Vancouver on Canada’s Pacific coast. A new 10-lane 2.2km Port Mann Bridge opened in 2012 (see box). It runs parallel to the o
  • Deeper but safer for trench shoring solutions from ThyssenKrupp’s e+s XL Carriage
    April 24, 2018
    ThyssenKrupp has deepened its range of trench shoring systems with its latest e+s XL Carriage solution. The e+s XL Carriage range allows a maximum working depth of 9m for jobs needing large-scale trenches such as concrete structures, rainwater retention basins, water collectors and deep pipe-laying projects. The maximum width of the end-supported shoring system is now 18m. ThyssenKrupp says that the system works well on sites where deeper work is required and there are no space restrictions, not least be
  • Pressure is on Superslim formwork
    February 4, 2025
    Temporary works specialist Altrad RMD Kwikform - Altrad RMDK - is helping realign the A452 road over a new rail line for England’s future high-speed trains.
  • Crane versatility helps with bridge building
    August 14, 2014
    The versatility and mobility of a Terex crawler crane has helped enormously with the construction of a new road bridge in Luxemburg. The Terex Superlift 3800 lattice boom crawler crane owned by Trier-based Steil Kranarbeiten was used to build a bridge in Luxemburg only two days after the same machine was used on a job in the Hunsrück mountain range. The machine was needed to lift a 440m long bridge across a valley, connecting a new section of highway.