For environmental reasons planners decided in favour of the challenging task of constructing a 13-field arched highway bridge over the Oparno Valley in the Bohemian area of the Czech Republic. The 258m bridge, whose reinforced concrete arch has a span of 135m, straddles the valley without any bridge piers, transferring the loads in the form of compressive forces into the foundations.
February 29, 2012 Read time: 3 mins
The 258m long and 50m high arched bridge crosses the Oparno Valley in the Bohemian Forest. (Photo: PERI GmbH)
For environmental reasons planners decided in favour of the challenging task of constructing a 13-field arched highway bridge over the Oparno Valley in the Bohemian area of the Czech Republic.

The 258m bridge, whose reinforced concrete arch has a span of 135m, straddles the valley without any bridge piers, transferring the loads in the form of compressive forces into the foundations.

Known as the A17 in Germany and D8 in the Czech Republic, the highway connects Dresden and Prague. This in turn is part of the pan-European corridor which extends to Budapest (Hungary) and then on to Istanbul (Turkey). In the Bohemian Forest section alone, between Rehlovice and Lovosice, three interchanges, two tunnels and a total of 29 bridges are being constructed along the 16km route.

As most of the stretch of highway currently under construction passes through a landscape conservation area, special requirements due to strict environmental protection regulations have to be met by both the planners and contractor for the realisation of this particular highway section.

With the help of a comprehensive 298 PERI formwork and scaffolding solution, two separate parallel structures are concurrently being constructed in both driving directions.

In close cooperation with the Prague-based building contractor Metrostav, PERI developed a cost-effective all-in-one solution using a standardised modular system with mostly rentable system components for the construction of the bridge elements. For the Oparno Bridge, the VARIOKIT engineering construction kit; RCS rail climbing system as well as PERI UP modular scaffold all played a key role. Construction of the supporting structures has been "very economical, optimally adapted to the individual project requirements."

The reinforced concrete arch is being constructed with the help of two customised formwork and scaffolding units in the form of a cantilevered construction. With this, the fresh concrete loads of the 5-6m long arched sections are transferred into the previously completed load-bearing sections.

During the moving procedure, hydraulic units provide the required lifting power so that work can be carried out without crane support, to a large extent, regardless of the weather.

The 53m formwork carriage and the formwork system itself are optimally configured to form a homogeneous supporting structure. For moving around the piers, the formwork is simply folded downwards. Mobile hydraulic pumps, which also ensure that the PERI RCS rail climbing system can operate crane-independently, allow the striking and shuttering procedures to take place.

The RCS rail climbing system for the erection of the bridge piers supplement the customised PERI modular system concept for the Oparno Bridge. The bridge piers are constructed in concreting cycle heights of between 3.1-3.6m with RCS climbing units. PERI UP stairs and access ladders as well as working platforms serve to allow personnel to reach and assemble the temporary bracing for the arched supporting structure.

For more information on companies in this article

Related Content

  • A new Indian cable-stayed bridge will improve transport connections
    March 2, 2015
    A major new cable-stayed bridge is being constructed in India - Partha Bratim Basistha reports. In India the construction of a major cable-stayed bridge is underway that will boost connections from capital Delhi to its surrounding areas. The bridge is being built in a bid to ease growing interstate traffic movement between Delhi and the surrounding North Indian states of Punjab, Uttar Pradesh, Haryana and Himachal Pradesh. Named Signature Bridge, this is a landmark structure due to its design aesthetics and
  • Self-climbing formwork solution for bridge pylons
    February 27, 2012
    Harsco Infrastructure has provided self-climbing formwork (SCF), which is helping ensure quick and safe access during the construction of a 320m tall pylon for the world’s longest cable-stayed bridge.
  • Engineering the Saadiyat Expressway
    February 24, 2012
    A new bridge, said to be the largest in the United Arab Emirates (UAE) in terms of area, is being constructed as part of a major highway project. The US$550 million Saadiyat Expressway project, which involves Leighton Construction (Abu Dhabi), related to one of Australia's largest contracting groups, in constructing a ten-lane, 6.5km long highway to link the UAE's main city, with an exclusive island lying just offshore.
  • RMD formwork for Qatar’s tallest bridge on Doha East Corridor
    July 6, 2016
    RMD Kwikform will be supplying tens of thousands of tonnes of its formwork and shoring for construction of Qatar’s tallest bridge on the Doha East Corridor project As well as the bridge, the Corridor contract comprises four interchanges at a total cost of US$612.5 million. Ashghal, Qatar's Public Works Authority, awarded the Corridor project to China Harbour Engineering Design and Construction. Built as a five-lane 11km bypass in Doha, the capital of Qatar, the project will also cater for a rail line