Amey chooses polystyrene blocks for Scottish tunnel infill

Amey recently completed an infill project to make safe a disused railway tunnel underneath the approach roads north of Scotland’s Forth Road Bridge. The 420m tunnel was part of the Dunfermline to North Queensferry railway line that provided a link to the ferry service until the opening of the Forth Bridge in 1890. The 4.3m-wide and 5.1m-high tunnel with vaulted roof and brick lining continued in use for freight until 1954. The tunnel runs underneath the A9000 and B981 on the northern approach to the Forth
June 25, 2018 Read time: 3 mins
Amey made light of the project by using expanded polystyrene (EPS) blocks
Amey recently completed an infill project to make safe a disused railway tunnel underneath the approach roads north of Scotland’s Forth Road Bridge.


The 420m tunnel was part of the Dunfermline to North Queensferry railway line that provided a link to the ferry service until the opening of the Forth Bridge in 1890. The 4.3m-wide and 5.1m-high tunnel with vaulted roof and brick lining continued in use for freight until 1954.

The tunnel runs underneath the A9000 and B981 on the northern approach to the Forth Road Bridge. Both tunnel ends had been sealed and the adjacent cuttings filled in, leaving a vertical shaft at each end as the only access points.

An 2958 Amey inspection had found parts of the tunnel degrading and in need of preventative maintenance to ensure continuing structural integrity. Due to the limited depth of cover above the tunnel, a failure could have had an impact on the roads overhead.

Two options were considered: an ongoing programme of inspection and maintenance or a one-off project to infill the tunnel with a low-cost material. The infill option was chosen because it would eliminate the need for future inspections or maintenance making it the more cost-effective solution in the long term.

After considering workforce safety, overall cost and the need to avoid disruption to the local community, it was decided to fill the tunnel with expanded polystyrene (EPS) blocks. These were manufactured to a specific compressive strength capable of resisting the weight of rock and tunnel lining in the event of a localised structural failure.

The EPS blocks were pre-cut to a size and weight to facilitate easy manual handling on-site. This allowed work to be carried out from the access shaft at the north end of the tunnel which would keep construction traffic out of the village of North Queensferry for the majority of the work.

Another advantage of the lightweight blocks was that they could be delivered in large lorryloads, significantly reducing the number of required vehicle movements.

Once offloaded, the blocks were passed down the access shaft and transported along the tunnel to the work face hooked onto a specially designed sliding monorail system.

The tunnel was first lined with a hydrocarbon-resistant membrane. Then 21,342 EPS blocks were literally walked into place and arranged to allow safe working at height.

Once the tunnel was infilled, the access shafts were filled with concrete to seal the tunnel and prevent damage to the blocks.

The job was completed by late March, said Mark Arndt, Amey’s operating company representative for the Forth Bridges Unit. “This has been an unusual project,” he said. “It’s a real measure of success that most local residents were not even aware this work was taking place, despite the tunnel emerging within metres of homes in North Queensferry.”

Before sealing the access shafts, local primary schoolchildren filled two time capsules with items of their choice which were then buried among the blocks. Unlike concrete or aggregate material, EPS blocks are easily removed if the tunnel needs to be reopened.

For more information on companies in this article

Related Content

  • Amey awarded Scottish strategic highways contract
    June 18, 2014
    Transport Scotland has awarded Amey a six-year contract to maintain and improve the motorways and trunk roads in South East Scotland. The commission, which is valued at over €115.3 million (£90 million), is subject to up to two one-year extensions and will see Amey deliver engineering design and operational delivery services for more than 885km (550 miles) of road. Under the Scottish Trunk Roads Unit South East (STRU SE) contract Amey will be responsible for managing and maintaining routes through Central
  • Montreal’s new Champlain Bridge is shaping up for Christmas
    September 10, 2018
    Montreal’s Champlain Bridges - one going up, one coming down, reports David Arminas The importance of the new Champlain Bridge to Montreal and Canada can’t be overstated, given the crumbling nature of the not-so-old original Champlain Bridge. The original steel truss affair across the St Lawrence River and the adjacent St Lawrence Seaway canal is “a lifeline for residents and businesses” in greater Montréal, according to the national Auditor General - the public sector spending watchdog. “It accommodates
  • Kenya’s bridge maintenance woes persist
    May 10, 2018
    Many of Kenya’s bridges are in poor condition writes Shem Oirere. The lack of programmed maintenance of bridges in Kenya continues to undermine the structural integrity of the infrastructure and compromising their general usage safety despite the existence of approved measures to protect them from falling into a state of disrepair. Experts think that both the absence of a maintenance component in bridge construction contracts, especially for those built one or two decades ago, and a weak maintenance supervi
  • Mullum Mullum Valley untouched by progress
    July 20, 2012
    Preserving the unspoiled Mullum Mullum Valley was the major consideration when deciding to build a traffic tunnel The answer to one of the major issues facing construction of the A$2.5 billion EastLink route in Australia was simple: construct a tunnel. While it was expensive, those involved realised they had little option but to go underground to protect the environmentally sensitive Mullum Mullum Valley, an untouched area of wood and bushland in Melbourne. EastLink, the 39km toll road project on the easter