Acrow supplies temporary bridge during Turcot Interchange project

Acrow Bridge has supplied a long-term temporary modular bridge to main contractor KPH Turcot for its work on the Turcot Interchange reconstruction in Montréal, Canada. The 32.3m-long Turcot modular steel bridge - Acrow’s longest clear span bridge in Canada – is 5m wide and has an orthotropic deck. The rented Acrow components arrived on site late last year and the bridge was opened to traffic in December. It is expected to be in place for two years. The Turcot Interchange is a three-level stack freeway int
June 28, 2018 Read time: 2 mins
Terex Bid-Well 3600 paver: LED lighting delivers additional visibility at night
Acrow Bridge has supplied a long-term temporary modular bridge to main contractor KPH Turcot for its work on the Turcot Interchange reconstruction in Montréal, Canada.

The 32.3m-long Turcot modular steel bridge - Acrow’s longest clear span bridge in Canada – is 5m wide and has an orthotropic deck. The rented Acrow components arrived on site late last year and the bridge was opened to traffic in December. It is expected to be in place for two years.

The Turcot Interchange is a three-level stack freeway interchange and the largest in the province of Québec. It is heavily travelled and carries an estimated 300,000 vehicles per day.

Because it is located in a high density residential and commercial area and links the Montréal-Pierre Elliott Trudeau International Airport with downtown Montréal, it is critical that traffic flow be maintained throughout the project.

Due to site restrictions, it was impossible to install the bridge using a crane. Instead, a full cantilever was designed using a 48.7m launching nose. The installer used pre-manufactured 3m sections and launched in sequence.

Acrow’s structure will allow vehicles to travel from northbound Autoroute 15 to westbound Autoroute 20 and keep workers safe, said Benoit Forget, Acrow’s regional director for Québec and New Brunswick provinces.

KPH Turcot - a partnership of Construction Kiewit and Parsons Canada, WSP Canada and Holcim Canada – won the design-build contract for the Turcot Interchange.

The overall US$2.9 billion Turcot programme is the largest in the Quebec province’s ministry of transport history. KPH Turcot’s design-build contract is the largest value portion of the programme.

When completed, the carbon-neutral project will provide 6.7km of multiuse trails, reduced maintenance costs as well as improved links between neighbourhoods. Also included will be more than 30hectares of green space and lower noise levels for nearby residents.

Also as part of the project, 145-lane-kilometres of roadways will be designed and constructed while Canadian National Railway mainline tracks will be relocated. Completion is set for 2020.

Related Content

  • Detroit-Windsor Tunnel crossing gets new customs facilities
    February 17, 2015
    The governments of Canada and the province of Ontario officially opened a new customs plaza at the Windsor-Detroit Tunnel, one of the busiest road crossings between the United States and Canada. The Canadian federal government provided US$8 and the province added $20 million for the project that is part of security improvements and to speed up people processing facilities on the Canadian side of the tunnel. Among the upgrades are new vehicle access lanes, new buildings for the Canada Border Services Agency
  • Repairing concrete roads using new technology
    July 28, 2015
    In the US state of Arkansas, a key stretch of concrete roads has been improved, allowing it to cope with current traffic volumes.
  • Israel interchange
    May 2, 2012
    A new US$350 million road project by the Israel National Roads Company will boost connectivity from the north to the centre of the country. The project is seeing the opening of new interchanges and roads in western Galilee. The aim of the project was to double the traffic capacity on Road 77, the Hamovil and Somech junctions and road No 79 that connects them.
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo