Skip to main content

Widening for key section of UK’s A11 route complete

Contractor Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the Highways Agency.
December 12, 2014 Read time: 2 mins
New A11 looking north, with the Elveden Memorial in the distance

Contractor 1146 Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the 2309 Highways Agency.

Main construction on the project started in January 2013 and the completed dual carriageway was officially opened by the Secretary of State for Transport, Patrick McLoughlin MP, at a ceremony attended by local stakeholders.

The scheme involved the widening of the strategic route linking Suffolk with Norfolk to dual two-lane standard along its length and included the construction of a 5.8km bypass to the north of Elveden village in Suffolk. It has also involved the construction of six major new bridge structures, forming either underpasses or overbridges.

330,000tonnes of earth were moved during the project, which also involved laying around 140,000tonnes of asphalt, lifting 1,500 tonnes of bridge steel work and pouring 4000 tonnes of concrete. Over 32km of drainage pipes and 50,000m3 of earth were replaced with gravel to take water away from the carriageway.

The scheme achieved 20% savings over its original projected cost as a result of nearly €25.2 million (£20 million) of savings by Balfour Beatty, including the avoidance of national grid and gas infrastructure diversions and the retention of more of the original A11 than originally anticipated. Some landscaping work will continue in the New Year and is due to be completed by the end of March 2015.

For more information on companies in this article

Related Content

  • Astaldi wins Polish S7 contract between Naprawa and Skomielna Biala
    March 3, 2016
    Astaldi, a global construction company based in Rome, has won a contract worth nearly €222 million for construction of Poland’s S7 dual carriageway between Naprawa and Skomielna Biala. The contract, awarded by the Polish General Directorate for National Roads and Motorways (GDDKiA), includes construction of a 2km tunnel under the Lubon Maly massif, 38 bridges and viaducts and three motorway services. There will also be 25km of access roads and two junctions. The north-south S7, when completed, will ru
  • Tarmac goes low-carbon on UK’s A64
    December 20, 2024
    The trial was delivered on a 2.4km section of England’s A64 strategic highway, the eastbound carriageway at junction 44 near the town of Bramham in North Yorkshire county.
  • Chinese investment
    February 6, 2012
    China's Ministry for Transport reveals that it beat its target for upgrading rural roads during 2009. Some 381,000km of rural roads were improved, beating the target of 300,000km by a considerable margin.
  • Raised dual carriageway reduces congestion
    February 21, 2012
    A new raised dual carriageway to bypass the historic centre of the City of Wroclaw in south-east Poland will give access to the new Miejski Stadium in time for its role in the UEFA Euro 2012 football finals.