Widening for key section of UK’s A11 route complete

Contractor Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the Highways Agency.
December 12, 2014 Read time: 2 mins
New A11 looking north, with the Elveden Memorial in the distance

Contractor 1146 Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the 2309 Highways Agency.

Main construction on the project started in January 2013 and the completed dual carriageway was officially opened by the Secretary of State for Transport, Patrick McLoughlin MP, at a ceremony attended by local stakeholders.

The scheme involved the widening of the strategic route linking Suffolk with Norfolk to dual two-lane standard along its length and included the construction of a 5.8km bypass to the north of Elveden village in Suffolk. It has also involved the construction of six major new bridge structures, forming either underpasses or overbridges.

330,000tonnes of earth were moved during the project, which also involved laying around 140,000tonnes of asphalt, lifting 1,500 tonnes of bridge steel work and pouring 4000 tonnes of concrete. Over 32km of drainage pipes and 50,000m3 of earth were replaced with gravel to take water away from the carriageway.

The scheme achieved 20% savings over its original projected cost as a result of nearly €25.2 million (£20 million) of savings by Balfour Beatty, including the avoidance of national grid and gas infrastructure diversions and the retention of more of the original A11 than originally anticipated. Some landscaping work will continue in the New Year and is due to be completed by the end of March 2015.

For more information on companies in this article

Related Content

  • Uretek delivers voided soils treatment for UK’s M3 Smart Motorway
    February 8, 2018
    Ground engineering specialist Uretek has been treating voided soils as part of maintenance following completion of the UK’s M3 Smart Motorway project. Work is between junctions 2 and 4a where Uretek has provided a non-disruptive alternative to conventional underpinning to solve foundation subsidence problems. The focus for Uretek is an old 900mm corrugated pipe, 73m long. The old pipe has had a new 700mm pipe inserted inside. However, the old pipe is rusting and rapidly deteriorating.
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Key Botswana road network gets an upgrade
    June 30, 2014
    Representing an investment of around US$113 million, Botswana’s A1 national road between Tonota and Francistown is undergoing a major upgrade This single-lane section is being progressively transformed into a north- and southbound dual carriageway, crossing four existing river bridges along the way. A strategically important transportation route for both Botswana and the southern African region, the A1 passes through Francistown, the nation’s second largest city, heading northwards to end at the Zimbabwe b
  • Machine control technology shortens road contract
    May 28, 2013
    The use of sophisticated machine control technology has helped halve the schedule required for a road contract – Jeff Winke. By using the latest machine control systems on the equipment fleet, a US contractor has managed to halve worker hours, machine time and overall costs. “We chopped 50% off the contract schedule,” said Jim Swenson, licensed professional land surveyor for Oregon Mainline Paving based in McMinnville, Oregon. “The project was completed a year ahead of the two-year schedule,” he explained