Contractor Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the Highways Agency.
December 12, 2014 Read time: 2 mins
New A11 looking north, with the Elveden Memorial in the distance

Contractor 1146 Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the 2309 Highways Agency.

Main construction on the project started in January 2013 and the completed dual carriageway was officially opened by the Secretary of State for Transport, Patrick McLoughlin MP, at a ceremony attended by local stakeholders.

The scheme involved the widening of the strategic route linking Suffolk with Norfolk to dual two-lane standard along its length and included the construction of a 5.8km bypass to the north of Elveden village in Suffolk. It has also involved the construction of six major new bridge structures, forming either underpasses or overbridges.

330,000tonnes of earth were moved during the project, which also involved laying around 140,000tonnes of asphalt, lifting 1,500 tonnes of bridge steel work and pouring 4000 tonnes of concrete. Over 32km of drainage pipes and 50,000m3 of earth were replaced with gravel to take water away from the carriageway.

The scheme achieved 20% savings over its original projected cost as a result of nearly €25.2 million (£20 million) of savings by Balfour Beatty, including the avoidance of national grid and gas infrastructure diversions and the retention of more of the original A11 than originally anticipated. Some landscaping work will continue in the New Year and is due to be completed by the end of March 2015.

For more information on companies in this article

Related Content

  • $889 million Texas deal for Balfour Beatty
    April 25, 2025
    Balfour Beatty has won an $889 million road deal in Texas.
  • New bypass for Meghalaya, India
    November 21, 2014
    A new two-lane road has been built in Meghalaya, India, providing a challenging project for the construction team The new road lies at a comparatively high altitude and provides a bypass around Shillong, the capital of Meghalaya and which is one of the smallest states in India. Shillong is located 1,496m above sea level, with the highest point being Shillong Peak at almost 2,000m, and the area has a much cooler climate than the rest of tropical India. Shillong is also only 55km away from Mawsynram, which is
  • HA dismantles footbridge over M5 in England
    January 3, 2013
    Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
  • Brisbane's highway of distinction
    August 2, 2012
    A massive AU$2 billion update of the Gateway Motorway in Queensland is underway to improve an infrastructure stretched by population boom. Report and photographs by Adrian Greeman Just 20 years after the Australian city of Brisbane built its Gateway Motorway with a high slim signature bridge dominating the river skyline, the road is being completely revamped. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels; the north is getting a completely