Widening for key section of UK’s A11 route complete

Contractor Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the Highways Agency.
December 12, 2014 Read time: 2 mins
New A11 looking north, with the Elveden Memorial in the distance

Contractor 1146 Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the 2309 Highways Agency.

Main construction on the project started in January 2013 and the completed dual carriageway was officially opened by the Secretary of State for Transport, Patrick McLoughlin MP, at a ceremony attended by local stakeholders.

The scheme involved the widening of the strategic route linking Suffolk with Norfolk to dual two-lane standard along its length and included the construction of a 5.8km bypass to the north of Elveden village in Suffolk. It has also involved the construction of six major new bridge structures, forming either underpasses or overbridges.

330,000tonnes of earth were moved during the project, which also involved laying around 140,000tonnes of asphalt, lifting 1,500 tonnes of bridge steel work and pouring 4000 tonnes of concrete. Over 32km of drainage pipes and 50,000m3 of earth were replaced with gravel to take water away from the carriageway.

The scheme achieved 20% savings over its original projected cost as a result of nearly €25.2 million (£20 million) of savings by Balfour Beatty, including the avoidance of national grid and gas infrastructure diversions and the retention of more of the original A11 than originally anticipated. Some landscaping work will continue in the New Year and is due to be completed by the end of March 2015.

For more information on companies in this article

Related Content

  • VIDEO: Dualling of UK’s A1 approved, finally
    June 10, 2024
    Costain was appointed main contractor in 2021 and expected to start on the project in mid-2022.
  • €2.27bn UK road investment in 2014 to support over 9,500 construction jobs
    November 11, 2013
    Over 9,500 construction jobs will be supported in 2014 by more than €2.27 billion (£1.9 billion) of investment in Britain’s roads, Transport Minister Robert Goodwill announced today. The total investment in 209 schemes is €5.15 billion (£4.3 billion), with the €2.27 billion to be spent in 2014 more than twice the amount being spent this year. Due to either start or be completed in 2014, these road programmes are estimated to boost the economy by over €22.52 billion (£18.8 billion) and are part of a €119.8
  • Economic gains from widening the A453 in Nottingham, England
    August 12, 2014
    Work is well underway on turning a busy just over 11km two-lane link road from the city of Nottingham to Junction 24 of the M1 in Leicestershire, England into a four-lane highway. The widened highway will relieve considerable peak-time congestion for travellers to Nottingham, the M1 and East Midlands Airport while also making journeys safer and more reliable. Guy Woodford reports Used by up to 30,000 vehicles a day, the A453 is renowned for congestion at peak travel times. But years of day-to-day commuter a
  • The Preston Western Distributor
    September 7, 2023
    Costain, as main contractor for the Preston Western Distributor project, was involved from the earliest stages, thanks to the UK’s Early Contractor Involvement approach. The project was delivered on time and on budget to the benefit of the local environment, local businesses and the region’s workforce. David Arminas reports*