Skip to main content

A wheely great bridge for the English city of Hull

A 60m pre-constructed pedestrian bridge weighing 150 tonnes as been wheeled into position over the A63 in the northern English city of Hull. The covered and vaulted Princess Quays Bridge will be renamed when it opens in the spring enabling pedestrians and cyclists to cross over the busy dual carriageway. The positioning operation meant that first the route was cleared of signage, guardrails and street lights. The bridge was then lowered onto two wheeled transporters – one at each end of the structur
November 6, 2019 Read time: 2 mins
Driving it home: Hull’s newest pedestrian bridge, above the busy A63, is carefully positioned and eventually lowered onto its foundations
A 60m pre-constructed pedestrian bridge weighing 150 tonnes as been wheeled into position over the A63 in the northern English city of Hull.


The covered and vaulted Princess Quays Bridge will be renamed when it opens in the spring enabling pedestrians and cyclists to cross over the busy dual carriageway.
 
The positioning operation meant that first the route was cleared of signage, guardrails and street lights. The bridge was then lowered onto two wheeled transporters – one at each end of the structure -  and ‘driven’ across Myton Street and along the westbound carriageway of the A63 to the marina.

Finally, the structure required a multiple point turn to position it above the pylons onto which it was lowered and secured.

The bridge is covered by a curving steel canopy and when finished will have sheltered viewing balconies at each end. As part of the bridge construction there will be new landscaped public areas at both the Princes Quay and marina sides.

The 8100 Highways England project, which is the first phase of the A63 Castle Street road improvement scheme, will help link the city’s marina with the southern end of Princes Quay Dock.

“Our team worked exceptionally hard throughout the weekend to move the street furniture, prepare the route and position the bridge by wheeling it to its final destination,” said Tom Peckitt, Highways England project manager. “The team worked throughout the night after the installation to reopen the A63 15 hours ahead of schedule.”

For more information on companies in this article

Related Content

  • Formwork developments in bridge construction
    February 23, 2012
    Major infrastructure projects worldwide are relying on innovative formwork solutions for speed and safety as Patrick Smith reports. The 970m long cable-stayed Golden Ears Bridge crossing the Fraser River in Vancouver, Canada, is the core element of a six-lane, highway project near the Canadian west coast.
  • Brisbane's highway of distinction
    August 2, 2012
    A massive AU$2 billion update of the Gateway Motorway in Queensland is underway to improve an infrastructure stretched by population boom. Report and photographs by Adrian Greeman Just 20 years after the Australian city of Brisbane built its Gateway Motorway with a high slim signature bridge dominating the river skyline, the road is being completely revamped. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels; the north is getting a completely
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Video: North Tyneside’s triple decker Silverlink on schedule
    August 29, 2018
    Highways England reports that the Silverlink triple-deck roundabout in North Tyneside is 80% complete and on schedule for opening in March next year. The €83 million project involves lowering the A19 highway underneath the Silverlink roundabout and A1058 Coast Road. The new road is expected to be used by 35,400 vehicles daily. “We are now entering the final stages,” said Steven Cox, Highways England assistant project manager. “Work to remove the 80,000m³ of soil has now been completed [and] we have six m