Video: North Tyneside’s triple decker Silverlink on schedule

Highways England reports that the Silverlink triple-deck roundabout in North Tyneside is 80% complete and on schedule for opening in March next year. The €83 million project involves lowering the A19 highway underneath the Silverlink roundabout and A1058 Coast Road. The new road is expected to be used by 35,400 vehicles daily. “We are now entering the final stages,” said Steven Cox, Highways England assistant project manager. “Work to remove the 80,000m³ of soil has now been completed [and] we have six m
August 29, 2018 Read time: 2 mins
Down she goes: the A19 highway is now underneath the Silverlink roundabout and A1058 Coast Road

8100 Highways England reports that the Silverlink triple-deck roundabout in North Tyneside is 80% complete and on schedule for opening in March next year.

The €83 million project involves lowering the A19 highway underneath the Silverlink roundabout and A1058 Coast Road. The new road is expected to be used by 35,400 vehicles daily.

“We are now entering the final stages,” said Steven Cox, Highways England assistant project manager.

“Work to remove the 80,000m³ of soil has now been completed [and] we have six months left on site. We still have some important work to complete such as the drainage, the pedestrian and cycle bridges and resurfacing the entire junction but providing the winter is kind to us we should be on track.”
 
Since work started in June 2016, 55 bridge beams, each weighing 35 tonnes and 22m long, have been transported from Ireland, three bridges have been constructed for the existing layout, and  have been used and 3.2km of drainage has been created.

Improvements to the 1.2km of cycleway have been carried out as well as adding another 247m.

A time capsule in which local businesses and schools have contributed items has been buried on site and will be unearthed in 100 years, explained Norma Redfearn, the new mayor of North Tyneside.

Highways England is the government-owned company responsible for modernising, maintaining and operating England’s motorways and major A roads.

For more information on companies in this article

Related Content

  • Northern Spire wins award from UK’s Association for Project Management
    November 30, 2018
    The Northern Spire bridge in Sunderland, northern England, has beaten off stiff competition to win another national construction and engineering award. The Spire, which opened in August this year at a cost of €132 million, was named Project of the Year: Engineering, Construction and Infrastructure 2018 by the UK’s Association for Project Management. The award is the latest honour for Sunderland’s 105m-tall cable-stayed bridge which links Castletown on the north side of the River Wear with Pallion.
  • New traffic solutions for the UK
    July 15, 2015
    Two major developments being introduced will help optimise traffic flow on routes carrying high volumes of vehicles/day. An installation of Flexicon’s flexible conduit will help keep the traffic flowing on one of the busiest sections of the M6 motorway through Birmingham by protecting power and data cabling for overhead gantries and CCTV cameras. On behalf of Highways England, who is implementing a hard shoulder running scheme between junctions 5 and 8, contractor’s Carillion is using the 63mm diameter L
  • Germany’s B-85 gets the treatment from Bomag’s BM 2200/75 planer
    February 23, 2018
    By this spring, Bomag’s new BM 2200/75 cold planer will have removed all the old pavement from a 2.6km section of Germany’s federal highway B-85. Work on the section between Amberg and Pittersberg started at the end of 2016 after the Ministry of Transport classified the road as being in “urgent need” of upgrading as part of the Federal Transport Infrastructure Plan. Actual roadworks began in mid-June 2017 after essential forestry work had been carried out, such as the removal of tree roots on both sides
  • Budimex and Strabag win 16km of Poland’s four-lane A1
    August 6, 2018
    Budimex and Strabag have won a contract to design and build 16km of Poland’s four-lane A1 highway between Tuszyn and Bełchatów. The €111 million deal with the Polish General Directorate for National Roads and Highways is scheduled for completion within 32 month, excluding winter months. The entire section will be concrete and includes two junctions, 17 bridges, several intersections and access roads, noise barriers and wildlife crossings.