Video: North Tyneside’s triple decker Silverlink on schedule

Highways England reports that the Silverlink triple-deck roundabout in North Tyneside is 80% complete and on schedule for opening in March next year. The €83 million project involves lowering the A19 highway underneath the Silverlink roundabout and A1058 Coast Road. The new road is expected to be used by 35,400 vehicles daily. “We are now entering the final stages,” said Steven Cox, Highways England assistant project manager. “Work to remove the 80,000m³ of soil has now been completed [and] we have six m
August 29, 2018 Read time: 2 mins
Down she goes: the A19 highway is now underneath the Silverlink roundabout and A1058 Coast Road

8100 Highways England reports that the Silverlink triple-deck roundabout in North Tyneside is 80% complete and on schedule for opening in March next year.

The €83 million project involves lowering the A19 highway underneath the Silverlink roundabout and A1058 Coast Road. The new road is expected to be used by 35,400 vehicles daily.

“We are now entering the final stages,” said Steven Cox, Highways England assistant project manager.

“Work to remove the 80,000m³ of soil has now been completed [and] we have six months left on site. We still have some important work to complete such as the drainage, the pedestrian and cycle bridges and resurfacing the entire junction but providing the winter is kind to us we should be on track.”
 
Since work started in June 2016, 55 bridge beams, each weighing 35 tonnes and 22m long, have been transported from Ireland, three bridges have been constructed for the existing layout, and  have been used and 3.2km of drainage has been created.

Improvements to the 1.2km of cycleway have been carried out as well as adding another 247m.

A time capsule in which local businesses and schools have contributed items has been buried on site and will be unearthed in 100 years, explained Norma Redfearn, the new mayor of North Tyneside.

Highways England is the government-owned company responsible for modernising, maintaining and operating England’s motorways and major A roads.

For more information on companies in this article

Related Content

  • EU missing target of halving road deaths by 2020, says ETSC
    April 12, 2018
    Halving the number of deaths on Europe’s roads by 2020 is not likely to be achieved, according to the European Transport Safety Council. The 28 members of the European Union reduced the number of road deaths by 20% from 2010-2017, far less than the 38% cut needed to stay on course to meet the 2020 target. The European Commission has just published data showing that deaths on EU roads fell by only 2% last year, following a similar decrease in 2016 and a 1% increase in 2015. “For four years in a row, the
  • Strong investment growth in the world’s highways was a key driver in John Deere and Wirtgen coming together
    December 21, 2017
    John Deere’s recent acquisition of the Wirtgen Group was driven by the way in which two leading equipment manufacturers could come together with no product overlap and target strong investment growth in the world’s highways sector
  • Delta Bloc solution for major upgrade to UK’s M6 motorway
    February 8, 2018
    Delta Bloc’s structural precast concrete barriers have been supplied for a €308 million smart motorway project being undertaken by Highways England on the M6 Motorway. UK contractor Charcon Construction Solutions worked with Delta Bloc UK, which develops, manufactures, supplies and installs permanent and temporary concrete road safety barriers. The Highways England scheme between junction 16 at Crewe and junction 19 at Knutsford has seen a new 32km concrete safety barrier installed in the central reservat
  • Rapid replacement of multiple bridges – the plan
    December 14, 2017
    The US State of Pennsylvania is saving itself $220 million over 10 years on a programme to replace 558 bridges with an unusual public private partnership approach - Kristina Smith writes It is called the Rapid Bridge Replacement Programme with good reason. Pennsylvania’s Department of Transport, PennDOT, wants to see no less than 558 structurally deficient bridges replaced with newly designed and constructed ones, all within four years. Using traditional forms of procurement this programme would be like