VIDEO footage shows bridge replacement project in Rhode Island

A time-lapse video has been released showing the rapid replacement of the Barton Corner Bridge in Rhode Island in the US. Rhode Island Department of Transportation (RIDOT) partnered with EarthCam to document the US$6.4 million rapid replacement of the Barton Corner Bridge. The construction project was completed during an 11-day period in August 2014 and can be seen in an exclusive time-lapse, released by RIDOT. Had RIDOT had used conventional methods, the bridge replacement would have taken two full constru
October 10, 2014 Read time: 2 mins
A time-lapse video has been released showing the rapid replacement of the Barton Corner Bridge in Rhode Island in the US. 3536 Rhode Island Department of Transportation (RIDOT) partnered with 7653 EarthCam to document the US$6.4 million rapid replacement of the Barton Corner Bridge. The construction project was completed during an 11-day period in August 2014 and can be seen in an exclusive time-lapse, released by RIDOT. Had RIDOT had used conventional methods, the bridge replacement would have taken two full construction seasons. By accelerating the construction process, the bridge was replaced in less than one month, saving money while eliminating traffic congestion.

The project was complex as the Barton Corner Bridge carries four lanes of I-95 plus two auxiliary lanes at a busy interchange with Route 2 on the Warwick/West Warwick line. Using accelerated bridge construction, RIDOOT built two halves of the bridge on land adjacent to the overpass, and then moved them into place. This enabled the new bridge to be constructed much faster compared with conventional construction methods, which would have taken twice the time. This approach also allowed RIDOT to do the work with no impact to Interstate traffic prior to installation.

EarthCam captured the innovative project from multiple angles by installing seven HD cameras in key locations.

Learn more about RIDOT and the Barton Corner Bridge replacement:

Time-Lapse: %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.dot.ri.gov/news/barton_corner/video.php Visit http://www.dot.ri.gov/news/barton_corner/video.php false http://www.dot.ri.gov/news/barton_corner/video.php false false%>

Facebook: %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.facebook.com/RIDOTNews Visit Facebook page false https://www.facebook.com/RIDOTNews false false%>

Twitter: %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal twitter.com/RIDOTNews Visit Twitter page false https://twitter.com/RIDOTNews false false%>

YouTube: %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.youtube.com/user/RIDOTwebmaster Visit RIDOT Youtube Page false https://www.youtube.com/user/RIDOTwebmaster false false%>

For more information on companies in this article

Related Content

  • CDE’s AggMax 83 logwasher gets an upgrade
    February 12, 2013
    Sitting alongside the M2500 mobile washing plant on CDE’s stand will be the latest AggMax 83 portable logwasher, which will include a RotoMax RX80 logwasher; triple- deck Prograde sizing screen and horizontal dewatering integrated on a single chassis. The AggMax has found many applications ranging from the washing of limestone conglomerate material in Scotland and Austria, to construction and demolition waste recycling in England, iron ore processing in India and sand and gravel washing in Germany.
  • Peri launched UP MDS Formwork at INTERMAT 2012
    January 6, 2017
    Peri is unveiling its new UP MDS shoring tower to all markets outside France at INTERMAT 2012. The shoring tower is equipped with working platforms hanging from the handrails, providing a high level of security during the erection and dismantling phases, and a significantly reduced exposure to musculoskeletal disorders (MSDs). The working platform sets an automatic working position 1m below the handrail and follows the top of the tower. The system improves productivity by optimising weight (total weight of
  • Peri launched UP MDS Formwork at INTERMAT 2012
    February 3, 2012
    Peri is unveiling its new UP MDS shoring tower to all markets outside France at INTERMAT 2012. The shoring tower is equipped with working platforms hanging from the handrails, providing a high level of security during the erection and dismantling phases, and a significantly reduced exposure to musculoskeletal disorders (MSDs). The working platform sets an automatic working position 1m below the handrail and follows the top of the tower. The system improves productivity by optimising weight (total weight of
  • SKF launches intelligent bearing technology
    January 6, 2017
    SKF Insight features intelligent wireless technology that enables bearings to communicate their operating conditions continuously, with internally powered sensors and data acquisition electronics. Bearings have long been considered the heart of rotating machinery but now SKF has made them the brain as well.