The UK’s A14 route is seeing a major upgrade

Work is progressing well on the project to upgrade the busy A14 route in the UK. A major milestone has been achieved with and important phase of the bridge installation having taken place. A 39m viaduct beam has been placed successfully for the bridge, which spans the River Ouse in Cambridgeshire. A key role in this work has been taken by the firm Cleveland Bridge UK. As part of Highways England’s £1.5 billion A14 Cambridge to Huntingdon improvement scheme, Cleveland Bridge was contracted by the A14 Integr
June 14, 2018 Read time: 2 mins
The A14 Viaduct being installed over the River Great Ouse
Work is progressing well on the project to upgrade the busy A14 route in the UK. A major milestone has been achieved with and important phase of the bridge installation having taken place. A 39m viaduct beam has been placed successfully for the bridge, which spans the River Ouse in Cambridgeshire.


A key role in this work has been taken by the firm Cleveland Bridge UK. As part of 8100 Highways England’s £1.5 billion A14 Cambridge to Huntingdon improvement scheme, Cleveland Bridge was contracted by the A14 Integrated Delivery Team (IDT) to design, fabricate and install a 750m viaduct bridge spanning the river and a large area of bordering flood plain on each bank.

Containing 6,000tonnes of steel and comprising 76 separate main girders and 800 cross girders, the structure was fabricated at Cleveland Bridge’s production facility in Darlington, County Durham before component parts were transported to site by road over a period of months. The majority of the main girders are 40m long, 2m deep and weigh 50tonnes.

The section of the bridge crossing the river has the longest span, so a complex series of girders has been installed to carry the weight of the greater load.

To enable the installation of the structure, including the most recent viaduct sections, a temporary platform was constructed under the length of the new bridge to provide a solid base for cranes and lorries.

However, to reduce time and site congestion, Cleveland Bridge utilised a 600tonne capacity crawler crane for the installation, which could lift all components for each section of the bridge from a single position at the side of the bridge. This meant fewer crane movements and no need to move the crane across the bridge footprint.

Chris Droogan, managing director of Cleveland Bridge UK, said: “The River Great Ouse viaduct is a showpiece element of the A14 project and is worthy of its place as one of Cleveland Bridge’s most significant structures in our history.”

“The viaduct will have a major impact on improving this part of the UK road network and we are very proud to have played a part in its development.”

For more information on companies in this article

Related Content

  • PERI's tall order in Mexico
    February 14, 2012
    The Baluarte Bridge (Puente Baluarte), part of a major highway project, ranks among the most outstanding infrastructure projects ever constructed in Mexico.
  • Brisbane's highway of distinction
    August 2, 2012
    A massive AU$2 billion update of the Gateway Motorway in Queensland is underway to improve an infrastructure stretched by population boom. Report and photographs by Adrian Greeman Just 20 years after the Australian city of Brisbane built its Gateway Motorway with a high slim signature bridge dominating the river skyline, the road is being completely revamped. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels; the north is getting a completely
  • Cleveland Bridge: monuments of culture, bridges that define
    July 2, 2021
    Bridges – many designed and renovated by Cleveland Bridge – are part of a city’s architectural landscape. They help define an urban area’s identity, as Carlos Arias*, the company’s international manager, explains in this special feature.
  • São Paulo's landmark bridge construction
    February 21, 2012
    To improve access from the east to São Paulo city centre, main contractor Construbase Engenharia is building a road complex comprising three viaducts and access ramps. The greatest challenge in Brazil's largest city is the showpiece Padre Adelino viaduct, a 122m long single-arch, single-span, cable-stayed concrete bridge moulded in situ with a parabola-shaped arch and a single-cell post-tensioned cantilever caisson