UK’s A14 route to open early

Highways England has announced that the UK’s A14 route is to open early.
By MJ Woof February 11, 2020 Read time: 2 mins
The new A14 route will cut congestion along a vital transport corridor for the UK – image ©courtesy of Highways England

Highways England has announced that the new A14 dual carriageway upgrade in the UK will open in the second quarter of 2020, some six months ahead of schedule. The project has cost £1.5 billion to carry out and is designed to reduce delays for transport between the East of England and the Midlands.

The first 19km bypass section of the new 34km route opened in late 2019, one year ahead of schedule. This important route is vital for the UK’s transport needs and carries around 85,000 vehicles/day, including 21,000 heavy vehicles/day. The A14 connects ports in East England with the West Midlands, a key hub for industry and logistics.

The project has been carried out to reduce congestion and delays through this part of the UK and the new A14 section will improve traffic flow and capacity considerably. The work has been carried out by a joint venture; the A14 Integrated Delivery Team. This comprises Balfour Beatty, Costain and Skanska, and design consultants Atkins and CH2M.

The project has previously won four awards at the 2019 British Construction Industry Awards. The awards were: Digital Transformation Initiative of the Year; Productivity Initiative of the Year; Partnership Initiative of the Year; Initiative of the Year Award.

Construction activity commenced on the project in November 2016, and the work has employed around 13,000 people in all. The new link will operate as an A road trunk route, instead of a motorway as had been originally planned.

As well as the Huntingdon southern bypass, the project includes an upgrade to the A14 between Swavesey and Milton, and a new local access road, the A1307, which runs parallel to it between Cambridge and Godmanchester. In addition, 38km of new facilities for vulnerable road users have also been included in the overall scheme.

The spring opening date will mark the end of permanent roadworks and reduced speed limits on the new A14 and the A1307. However, the project team will still need to carry out landscaping, installing new traffic management technology, and work in the verges. Some temporary overnight closures or off-peak daytime lane closures will be needed.

Related Content

  • Esri and Heliguy to cooperate
    February 15, 2021
    Esri UK has signed a partnership with drone developer Heliguy as part of its strategy to offer all elements of a drone service.
  • Australia road widening project in Queensland
    November 3, 2017
    The preparatory work is underway for a stretch of the Ipswich Motorway widening project in Queensland Australia. The project is worth around US$318.6 million (A$400 million). This first section of the widening work is 3km long and runs from Granard Road at Rocklea to the Oxley roundabout. The work involves widening the route from four lanes at present to six lanes and improving seven bridges, which includes increasing the height of the bridge over Oxley Creek. The 10km widening project is intended to reduce
  • Texas highway project awarded
    May 31, 2019
    A joint venture team has been awarded the US$1.7 billion I-635 LBJ East infrastructure project in Dallas, Texas. Fluor Corporation heads the joint venture, which also includes Balfour Beatty Infrastructure. The partners will carry out the contract to design and construct the I-635 LBJ East Project in Dallas for the Texas Department of Transportation (TxDOT). The scope of work includes the widening and full reconstruction of nearly 18km of the I-635 route, which is also known as LBJ Freeway. In addition, th
  • Effective stabilisation
    February 24, 2012
    Contractor BAM Nuttall and specialist piling sub contractor Aarsleff Piling, have been working closely to develop a cost-effective solution to a tricky piling problem. The two firms have developed an alternative and versatile technique to reduce the risk of delays installing 2,150 precast concrete piles along part of the route of an innovative guided busway in Cambridgeshire in the UK.