Skip to main content

UK’s A14 route to open early

Highways England has announced that the UK’s A14 route is to open early.
By MJ Woof February 11, 2020 Read time: 2 mins
The new A14 route will cut congestion along a vital transport corridor for the UK – image ©courtesy of Highways England

Highways England has announced that the new A14 dual carriageway upgrade in the UK will open in the second quarter of 2020, some six months ahead of schedule. The project has cost £1.5 billion to carry out and is designed to reduce delays for transport between the East of England and the Midlands.

The first 19km bypass section of the new 34km route opened in late 2019, one year ahead of schedule. This important route is vital for the UK’s transport needs and carries around 85,000 vehicles/day, including 21,000 heavy vehicles/day. The A14 connects ports in East England with the West Midlands, a key hub for industry and logistics.

The project has been carried out to reduce congestion and delays through this part of the UK and the new A14 section will improve traffic flow and capacity considerably. The work has been carried out by a joint venture; the A14 Integrated Delivery Team. This comprises Balfour Beatty, Costain and Skanska, and design consultants Atkins and CH2M.

The project has previously won four awards at the 2019 British Construction Industry Awards. The awards were: Digital Transformation Initiative of the Year; Productivity Initiative of the Year; Partnership Initiative of the Year; Initiative of the Year Award.

Construction activity commenced on the project in November 2016, and the work has employed around 13,000 people in all. The new link will operate as an A road trunk route, instead of a motorway as had been originally planned.

As well as the Huntingdon southern bypass, the project includes an upgrade to the A14 between Swavesey and Milton, and a new local access road, the A1307, which runs parallel to it between Cambridge and Godmanchester. In addition, 38km of new facilities for vulnerable road users have also been included in the overall scheme.

The spring opening date will mark the end of permanent roadworks and reduced speed limits on the new A14 and the A1307. However, the project team will still need to carry out landscaping, installing new traffic management technology, and work in the verges. Some temporary overnight closures or off-peak daytime lane closures will be needed.

Related Content

  • Cleveland Bridge UK’s A14 work shortlisted
    July 15, 2020
    The showpiece bridge for A14 project is the 750m-long viaduct over River Great Ouse.
  • Major road widening project for Cambridgeshire
    May 12, 2016
    Work to upgrade the A14 route in Cambridgeshire now looks set to commence at the end of 2016. The A14 will be widened along a 33.6km stretch as part of a programme of works to increase its capacity. The work will also involve building a new bypass around Huntingdon as well as widening a section of the A1. The project also includes making a series of improvements to five junctions situated along the route, located at Bar Hill, Swavesey, Girton, Histon and Milton. In all the work is expected to cost some £1.5
  • The UK’s A14 route is seeing a major upgrade
    June 14, 2018
    Work is progressing well on the project to upgrade the busy A14 route in the UK. A major milestone has been achieved with and important phase of the bridge installation having taken place. A 39m viaduct beam has been placed successfully for the bridge, which spans the River Ouse in Cambridgeshire. A key role in this work has been taken by the firm Cleveland Bridge UK. As part of Highways England’s £1.5 billion A14 Cambridge to Huntingdon improvement scheme, Cleveland Bridge was contracted by the A14 Integr
  • Highways England awards €2.1 billion of upgrades for UK motorways
    August 7, 2015
    Highways England has today appointed six joint-venture companies to design and build 10 “smart motorways” as part of a €2.1 billion investment. Construction contractors appointed are the Balfour Beatty and VINCI joint venture, a Costain and Galliford Try joint venture, as well as a Carillion and Kier joint venture. Designers are a CHM2 and Hyder joint venture, an Amey and Arup joint venture, as well as a Jacobs and Atkins joint venture. The award is the second major procurement to be given under th