UK’s A14 route to open early

Highways England has announced that the UK’s A14 route is to open early.
By MJ Woof February 11, 2020 Read time: 2 mins
The new A14 route will cut congestion along a vital transport corridor for the UK – image ©courtesy of Highways England

Highways England has announced that the new A14 dual carriageway upgrade in the UK will open in the second quarter of 2020, some six months ahead of schedule. The project has cost £1.5 billion to carry out and is designed to reduce delays for transport between the East of England and the Midlands.

The first 19km bypass section of the new 34km route opened in late 2019, one year ahead of schedule. This important route is vital for the UK’s transport needs and carries around 85,000 vehicles/day, including 21,000 heavy vehicles/day. The A14 connects ports in East England with the West Midlands, a key hub for industry and logistics.

The project has been carried out to reduce congestion and delays through this part of the UK and the new A14 section will improve traffic flow and capacity considerably. The work has been carried out by a joint venture; the A14 Integrated Delivery Team. This comprises Balfour Beatty, Costain and Skanska, and design consultants Atkins and CH2M.

The project has previously won four awards at the 2019 British Construction Industry Awards. The awards were: Digital Transformation Initiative of the Year; Productivity Initiative of the Year; Partnership Initiative of the Year; Initiative of the Year Award.

Construction activity commenced on the project in November 2016, and the work has employed around 13,000 people in all. The new link will operate as an A road trunk route, instead of a motorway as had been originally planned.

As well as the Huntingdon southern bypass, the project includes an upgrade to the A14 between Swavesey and Milton, and a new local access road, the A1307, which runs parallel to it between Cambridge and Godmanchester. In addition, 38km of new facilities for vulnerable road users have also been included in the overall scheme.

The spring opening date will mark the end of permanent roadworks and reduced speed limits on the new A14 and the A1307. However, the project team will still need to carry out landscaping, installing new traffic management technology, and work in the verges. Some temporary overnight closures or off-peak daytime lane closures will be needed.

Related Content

  • Safety issues fuel interest at PIARC’s tunnel conference in Lyon
    June 4, 2019
    Alternative fuel and automated vehicle issues occupied minds at PIARC’s first international road tunnel safety conference. David Arminas reports from Lyon More than ever, tunnel management must done in a wholistic fashion, said Andre Broto, president of PIARC, the World Road Association, based in Paris. With those sentiments, Broto kicked off PIARC’s first International Conference on Tunnel Operations and Safety. One of the first speakers, Sandrine Bernabei Chinzi, head of transport infrastructure at Fr
  • Linking Kenya and Uganda with a new road project
    May 10, 2018
    An upgraded road link will improve transport between Uganda and Kenya - Shem Oirere reports Rainfall patterns and type of soil in an agricultural rich area shared by the neighbouring East African countries of Kenya and Uganda was a key consideration in arriving at the decision to upgrade to bitumen standards 73km of the 118km Kapchorwa-Kitale road that links the two countries. Initially, Uganda had proposed to have the road between Kapchorwa and Suam on its border with Kenya re-gravelled and widened to a
  • UK council plans €64 million highways upgrade
    August 17, 2012
    UK-based Milton Keynes Council is to borrow €64 million (£50 million) for a new road repair programme to tackle the city’s “decaying" roads and pavements. The 1960’s new town, which is located about an hour’s drive north of London, has approved a plan which includes more than €27 million (£21 million) for vital road repair work, €18 million (£14 million) to tackle its ageing bridges and more than €9 million (£7 million) to restore the council’s pavement and footpath network.
  • Greener transport infrastructure
    February 16, 2024
    Crossing the carbon challenge: Pioneering carbon reduction on the UK’s ‘greenest’ major infrastructure project Paul Taylor – AtkinsRéalis Carbon Manager, Lower Thames Crossing Roads North