Three Colombian bridge projects commencing

In Colombia progress is being seen on three major bridge projects located in different parts of the country. Construction of the new Pumajero Bridge is well in hand and is expected to be complete before the end of 2019. The new PumajeroBbridge will be 2,247m in length and have 990m of viaduct connections and access, as well as two three-lane carriageways on each side. Once the new bridge is open to traffic, the old cable-stayed concrete link between Baranquilla and Sitionuevo will be demolished. The new
January 17, 2019 Read time: 3 mins

In Colombia progress is being seen on three major bridge projects located in different parts of the country.

Construction of the new Pumajero Bridge is well in hand and is expected to be complete before the end of 2019. The new PumajeroBbridge will be 2,247m in length and have 990m of viaduct connections and access, as well as two three-lane carriageways on each side. Once the new bridge is open to traffic, the old cable-stayed concrete link between Baranquilla and Sitionuevo will be demolished.

The new bridge provides a height of 45m over the Magdalena River, allowing vessels to pass underneath. When complete the bridge will be Colombia’s longest and will provide a new link between Santa Marta and Baranquilla.

Constructed in 1974, the old bridge has restricted river traffic due to its low height and is too narrow to cope with the vehicle numbers it has to carry. Its design prompted controversy even when it was built but the new link will address the transport shortcomings over the earlier structure.

Meanwhile, construction work will restart on the Chirajara Bridge in the second quarter of 2019. The French contractor 5871 Eiffage will carry out the work, which is expected to cost US$31.7 million. Construction work on the bridge was halted in January 2018 after part of the structure collapsed. The project is being managed by Concesionaria Vial de los Andes (Coviandes)

At the same time, concern has been expressed over the Hisgaura Bridge as to its safety. The $33 million project is being carried out by Spanish contractor Sacyr. Although the bridge is said to be safe, its construction does not meet the requirements of the agreement set by Colombian funding agency Fondo Adaptacion. The problems is with the central span, which rather than being flat now has an uneven, undulating deck. It is not clear how this issue occurred during construction or how best to alleviate the problem. But Colombia's national road institute (Invias) is less than impressed and is now looking to gain compensation from Sacyr over the Hisguara Bridge project as a result.

The bridge forms part of the Málaga—Los Curos highway, which will improve transport between Colombia’s Boyacá Region and Santander Region. The Hisgaura Bridge measures 653m in length with a single span reaching 400m.

There has also been criticism over the poor standard of the access roads to the Hisgaura Bridge. But paving work is now underway on 70km of access roads and this will be completed by 2020. Work to the remaining 50km will be finished at a later date.

For more information on companies in this article

Related Content

  • Tunnel project of Chilean capital Santiago
    April 8, 2015
    Tunnel construction in Chilean capital Santiago will help cut chronic congestion – Mauro Nogarin & Mike Woof write. Chile’s capital Santiago is a thriving city having benefited from the country’s economy growing strongly in recent years. The massive copper mining sector has helped boost the country’s GDP significantly in the past few decades, also aided by the growing international reputation of Chile’s large wine industry. The steady economic growth has resulted in an equally steady growth in average incom
  • Colombia’s key road transport projects
    May 10, 2019
    A series of major road transport projects are moving ahead in Colombia, with the country’s national infrastructure agency (ANI), handling most of the deals. In the country’s capital, Bogota, design work is now complete on the Calle 13 and Accesos Norte II road projects. The Calle 13 project will see an 11.5km section of route widened so that it features three lanes in either direction. The work will also include building new facilities for pedestrians and cyclists. This project is expected to cost US$1.15 b
  • Colombia’s delayed La Linea Tunnel and tertiary road development programme seeing progress
    July 6, 2017
    Progress is now being seen in Colombia with regard to key tunnel and road projects. A consortium comprising Conconcreto and CSS Constructores is to complete the 12% of work still needed to finish the La Linea Tunnel project.
  • Major bridge widening project going to plan
    May 2, 2012
    When built it was determined that a vital US road/rail bridge would always be widened.