Three Colombian bridge projects commencing

In Colombia progress is being seen on three major bridge projects located in different parts of the country. Construction of the new Pumajero Bridge is well in hand and is expected to be complete before the end of 2019. The new PumajeroBbridge will be 2,247m in length and have 990m of viaduct connections and access, as well as two three-lane carriageways on each side. Once the new bridge is open to traffic, the old cable-stayed concrete link between Baranquilla and Sitionuevo will be demolished. The new
January 17, 2019 Read time: 3 mins

In Colombia progress is being seen on three major bridge projects located in different parts of the country.

Construction of the new Pumajero Bridge is well in hand and is expected to be complete before the end of 2019. The new PumajeroBbridge will be 2,247m in length and have 990m of viaduct connections and access, as well as two three-lane carriageways on each side. Once the new bridge is open to traffic, the old cable-stayed concrete link between Baranquilla and Sitionuevo will be demolished.

The new bridge provides a height of 45m over the Magdalena River, allowing vessels to pass underneath. When complete the bridge will be Colombia’s longest and will provide a new link between Santa Marta and Baranquilla.

Constructed in 1974, the old bridge has restricted river traffic due to its low height and is too narrow to cope with the vehicle numbers it has to carry. Its design prompted controversy even when it was built but the new link will address the transport shortcomings over the earlier structure.

Meanwhile, construction work will restart on the Chirajara Bridge in the second quarter of 2019. The French contractor 5871 Eiffage will carry out the work, which is expected to cost US$31.7 million. Construction work on the bridge was halted in January 2018 after part of the structure collapsed. The project is being managed by Concesionaria Vial de los Andes (Coviandes)

At the same time, concern has been expressed over the Hisgaura Bridge as to its safety. The $33 million project is being carried out by Spanish contractor Sacyr. Although the bridge is said to be safe, its construction does not meet the requirements of the agreement set by Colombian funding agency Fondo Adaptacion. The problems is with the central span, which rather than being flat now has an uneven, undulating deck. It is not clear how this issue occurred during construction or how best to alleviate the problem. But Colombia's national road institute (Invias) is less than impressed and is now looking to gain compensation from Sacyr over the Hisguara Bridge project as a result.

The bridge forms part of the Málaga—Los Curos highway, which will improve transport between Colombia’s Boyacá Region and Santander Region. The Hisgaura Bridge measures 653m in length with a single span reaching 400m.

There has also been criticism over the poor standard of the access roads to the Hisgaura Bridge. But paving work is now underway on 70km of access roads and this will be completed by 2020. Work to the remaining 50km will be finished at a later date.

For more information on companies in this article

Related Content

  • New chapter for bituminous slurry in Colombia
    January 11, 2019
    Colombia’s San Rafael road concessionaire is using its first VSB Macropaver 12B unit to maintain a road carrying heavy traffic volumes – Enrique Saez writes The use of bituminous slurry for road maintenance works in Colombia is taking a new step forward with the purchase of equipment from VSS Macropaver by road contractors in the country. Engineer Ezequiel Romero, manager of the concessionaire San Rafael, explained that the application of bituminous grout has delivered major benefits for the firm. The c
  • New bridge for Lowestoft in Suffolk
    November 1, 2019
    The tender process is being restarted for a new bridge in Lowestoft. The project is expected to cost some €68.2 million. The bridge will be designed so that it can be raised, allowing vessels to pass underneath. This will be the third crossing spanning Lake Lothing. Unlike the existing bascule bridge however, the new structure will provide a higher clearance so that some vessels will be able to pass underneath without having to raise the bridge, reducing traffic disruption on the road link. When complete, t
  • Peru's capital road revamp
    February 15, 2012
    The new Via Parque Rimac road project in Peruvian city Lima is expected to cost some US$700 million. The city authorities plan to merge the Linea Amarilla express way project with the Rio Verde project, a development that comes after an agreement with Linea Amarilla (Lamsac), which is building the Linea Amarilla.
  • Road upgrades for Colombia’s Boyaca
    March 6, 2019
    A series of road upgrades are planned for Colombia’s Boyaca Department for the 2019-2020 period. One of the projects will be for work to a 20km section of the Transversal de Boyaca Route 60, which connects to the Magdalena Medio. Work will also be carried out on the Crucero-Pajarito stretch of the Transversal del Cusiana Route 62, including several bridge upgrades. Repaving work will be carried out on the Duitama-Presidente stretch of Route 55. Paving work is also planned for tertiary roads. In all 77km of